Dhaka Mass Transit Company Limited (DMTCL) has formed an investigation committee regarding the suspension of metro rail movement due to zero voltage of Overhead Catenary System (OCS) on Sunday.
Managing Director of DMTCL MAN Siddique told the media on Sunday.
He said: "The investigation committee has been asked to submit its report within the next 7 days.We will know then if the issue was internal or external.”
Overhead catenary systems require 1,500 volts to run trains. And the OCS at each station is different. Sometimes the voltage goes up and down.
The power supply on both the lines suddenly became zero in the Pallabi section. After being closed for about two and a half hours, the metro rail movement was normalized around 4:30pm.