The government has started taking strict measures against officials found involved in massive financial irregularities in the 2020-21 fiscal year regarding a project of the Department of Shipping to install lighthouses and coastal radio stations along the coastline.
The allegations include payment of Tk22 lakh per month to an interpreter of the project and withdrawal of salaries and bills in the name of a driver who does not exist.
The interpreter, Jasim Sheikh, of contractor South Korea-based Sami Construction Limited, was given Tk2,68,61,400 in one year from the building and installation sector of the project in the 2021-22 fiscal year.
On the other hand, Anwar Shikder and Md Ansar Ali were appointed through outsourcing from the project money. Salary and bills were withdrawn in the name of the two drivers. But in reality no driver named Ansar Ali was found during an audit.
In addition to these unusual bills, Project Director (PD) Abu Saeed Delwar Rahman himself took Tk7,26,840 from the administrative expenditure sector, but it was not mentioned in the cash register of the project. The PD's office could not provide any documents on this withdrawal. As a result, Section 5 of the Public Procurement Rules (PPR)-2008 has been violated, the report said.
Discrepancies surrounding the highly sophisticated and crucial project were highlighted in the report of the internal audit committee of the department.
After various complaints surfaced about the project, the then director general of the Shipping Department, Commodore Nizamul Haque, formed an internal audit committee of four members on April 10 this year. The committee formed under the leadership of Badrul Hasan Liton, former director of the department and deputy secretary of the government, submitted the report on April 21, following which the government started taking action, including the suspension and transfer of several officials.
According to the report, not all the bills for the financial years 2021-22 and 2022-23 are available, but many discrepancies have been found after reviewing the insufficient bills. The report commented that the Bills PPR-2008, delegation of government financial powers and government regulations including circulars of the Ministry of Finance were not properly followed.
CourtesyDuring the audit, huge irregularities were found in the financial expenditure of the project at various stages. The probe committee did not get the necessary cooperation from the office of the project director and the Office of the Audit and Accounting Officer of the ministry. Even despite the oral instructions of the Comptroller General, the officials concerned did not provide sufficient information, the report said.
The government started implementing the project with financial assistance from South Korea in 2014, nearly a decade after preparations, when the Ecnec passed the Tk370 crore project on March 11. The previous year, Bangladesh and South Korea signed a loan agreement to implement the project. The feasibility study was completed in December 2011.
Over the years, the project cost has increased to Tk779 crore.
The probe report says Tk123,08,46,600 was spent through the Audit and Accounting Officer of the ministry in the 2021-22 fiscal year.
Anomalies in 2021-22
According to the audit report, Tk5,13,19,277 has been given to two companies named Moon View Development Limited and Jumaimah International (JV) from the buildings and structures sector for the financial year 2021-22. Moon View Development received the amount on June 15 last year.
However, the ministry's accounting office did not provide the bill when sought by the probe committee. The ministry also could not produce the measurement books of the work completed.
According to the report, RKS Traders has been paid Tk9,67,600 and Tk1,93,520 from the fee, charge and commission sector and Tk2,42,720 from the machinery and equipment sector. However, the ministry provided one of the three bills.
On the other hand, Tk5,33,328 was paid in two separate tokens on the same day (June 15, 2022) from the furniture and fittings and fixers sub-sector of the repair and preservation sector. The project officials kept an assistant director of the Directorate General of Jute in the Tender Quotation Committee but did not take the permission of the Director General of the Department of Shipping.
Though they used the address of the Department of Shipping's head office in different letters, the officers and employees of the project have separate offices at different addresses.
Irregularities in 2022-23
The probe committee has received information on the expenditure of Tk17,18,66,400 for the project in the fiscal year 2022-23 from the ministry's accounting office. Out of this, Tk15,51,69,100 has been spent in the non-residential building sector. Among these sums, Sami Construction has taken Tk3,11,42,802 and Tk2,02,80,000 in two bills. But no measurement books or site books were given to the committee. The remaining amount was given to two companies named CDDL and Speedy Group.
According to sources, bills of Tk63,65,400 have been paid to three organizations – Engineering Survey and Design, Bates Consultant and Pulse Consultant – from the consultancy sub-sector of professional services, honorarium and special rate sector. The committee did not find any evidence of the approval of the Department of Shipping which is required during such payments.
Besides, in the case of the appointment of Bates Consultants, subsections 1-6 of Section 110 of the PPR-2008 were not followed. According to the report, the committee did not get the site book information in the bill of Pulse Consultants.
Besides, Tk1,22,67,891 has been paid to Speedy Group from the non-residential building sector on March 19 of this year without following the tender rules. Moreover, tender notices were published in two insignificant Bengali and English newspapers, namely, the daily Ajker Prabhat and The Daily Earth.
Former director general of the Water Resources Planning Organisation (Warpo) M Inamul said it is not acceptable at all that the monthly salary of a Bangladeshi interpreter in a small project is Tk22,38,450. Besides delays in the implementation of the project, unlimited irregularities and corruption have surfaced at every stage.
He called for transparency and accountability by bringing the corrupt officials and parties under the law.
Shipping Secretary Mustafa Kamal said that the authorities have learned about all the allegations. “Those who are guilty must be punished,” he added.