A delay of one and a half years has raised the cost by 14.75% of appointing consultant for building another runway and terminal at Shahjalal airport.
On December 5, 2012, the Civil Aviation Ministry approved the appointment of consultant at a cost of Tk33.8 crore.
However, the Bureau of Research,Testing and Consultation of Buet took nearly a year and a half to recently select the joint venture of three firms – Yooshin Engineering Corporation from South Korea, CPG Consultants Pte Ltd of Singapore andDevelopment Design Consultants Ltd of Bangladesh.
Because of the delay, the consultants would now have to paid Tk38.78 crore – nearly Tk5 crore extra.
An official of the Civil Aviation ministry said nearly 60% of the Shahjalal Airport’s 809 hectare area had remained utilised.
“Although it would be hard to ensure 100% utilisation, we could most definitely ensure double usage of the current capacity,” he said.
According to the ministry, the Dhaka airport currently handles around 40 lakh passengers every year up against a capacity to handle 80 lakh.
A busy international airport should facilitate at least 60 takeoffs and landings per hour; but officials said Shahjalal could now host only 10 aircrafts every hour.
Aviation specialists said if the current capacity could be doubled through proper utilisation of land, then there would be no need to think about an alternative in the next 25 years.
A ministry proposal for finalising the consultants would be placed in today at the meeting of the cabinet committee on public purchase.
Earlier, the duration of the project for constructing the additional infrastructures was extended by nine months by the ministry.
Civil Aviation and Tourism Minister Rashed Khan Menon told the Dhaka Tribune yesterday that: “The appointment of consultant has been delayed by one and a half years because of the lengthy evaluation and tender processes. But now we hope that after the implementation of the project, Shahjalal airport’s capacity will be enhanced.”
The busiest Frankfurt and Heathrow airports, both with two runways, now each handle more than 3 crore passengers annually.
They suggested that the Chittagong airport, which has a capacity of handling 80 lakh passengers, should be used more. At present the airport in the port city utilises only 30% of its capacity.