According to railway officials, the total cost of the project is Tk3,801.61cr. Of this, Tk1,149.89cr will be spent for the rail line and other civil works and Tk1,076.45cr will be spent for bridges and culverts. The rest has already been spent for land acquisition.
Majibur Rahman told the Dhaka Tribune that the project would be implemented in three phases: construction of the rail line, construction of bridges and the telecommunication and signaling system for traffic.
The Executive Committee of the National Council (Ecnec) approved the project on December 21, 2010 with a cost Tk1,700.21cr under joint funding by Bangladesh and India.
However, the slow progress has almost doubled the cost. On May 27, 2015, the Ecnec approved a revised cost of Tk3,801.61cr. Of this, India will provide Tk2,300.71cr as soft loan under the Indian line-of-credit and the government will pay the rest.
The government faced some trouble renegotiating the funds from India when the cost increased by around 121%.
The main construction work began early this year. Indian Ircon Limited is developing the rail line and the Larsen and Toubro Limited is building the Rupasa bridge following two separate deal with BR.The priority projects of Bangladesh Railways (BR) are moving at a snail's pace.
The ruling Awami League government committed to connecting the Mongla seaport with the Chittagong port through railway, which will also create a network between the neighbouring countries of India, Nepal, Bhutan and Myanmar. The project, when completed, is expected to boost the country's trade and economy.
Although dormant for a long time, in this last year of the government's tenure the Khulna-Mongla rail link project has begun moving at a fast pace. But its current progress is only 31% which makes its completion by the scheduled deadline in June 2018 highly unlikely.
The 86.87km long Khulna-Mongla rail line project was launched on December 1, 2010 with an aim to finish by June 2014, but the project authority later updated the deadline.
According to railway officials, land acquisition work of around 750 acres is complete and land development work is progressing in most of the project area.
Work on the 86.87km long rail link, including loop lines, a rail bridge over the Rupsha River, 21 small bridges, 110 culverts and eight stations, has not begun, said officials.
“The project faced delays but now it is moving at a high speed and hopefully most of the work will be done by the deadline,” said Majibur Rahman, project director.
Shamsul Hoque, a professor of civil engineering at Bangladesh University of Engineering and Technology, told the Dhaka Tribune: “The Khulna-Mongla rail link is one of the top priority projects. It could play a vital rule to boost the economy by connecting the two seaports.
“Already six or seven years have gone by due to the negligence of government officials. This has raised the project cost,” he said.
According to railway officials, the total cost of the project is Tk3,801.61cr. Of this, Tk1,149.89cr will be spent for the rail line and other civil works and Tk1,076.45cr will be spent for bridges and culverts. The rest has already been spent for land acquisition.
Majibur Rahman told the Dhaka Tribune that the project would be implemented in three phases: construction of the rail line, construction of bridges and the telecommunication and signaling system for traffic.
The Executive Committee of the National Council (Ecnec) approved the project on December 21, 2010 with a cost Tk1,700.21cr under joint funding by Bangladesh and India.
However, the slow progress has almost doubled the cost. On May 27, 2015, the Ecnec approved a revised cost of Tk3,801.61cr. Of this, India will provide Tk2,300.71cr as soft loan under the Indian line-of-credit and the government will pay the rest.
The government faced some trouble renegotiating the funds from India when the cost increased by around 121%.
The main construction work began early this year. Indian Ircon Limited is developing the rail line and the Larsen and Toubro Limited is building the Rupasa bridge following two separate deal with BR.
According to railway officials, the total cost of the project is Tk3,801.61cr. Of this, Tk1,149.89cr will be spent for the rail line and other civil works and Tk1,076.45cr will be spent for bridges and culverts. The rest has already been spent for land acquisition.
Majibur Rahman told the Dhaka Tribune that the project would be implemented in three phases: construction of the rail line, construction of bridges and the telecommunication and signaling system for traffic.
The Executive Committee of the National Council (Ecnec) approved the project on December 21, 2010 with a cost Tk1,700.21cr under joint funding by Bangladesh and India.
However, the slow progress has almost doubled the cost. On May 27, 2015, the Ecnec approved a revised cost of Tk3,801.61cr. Of this, India will provide Tk2,300.71cr as soft loan under the Indian line-of-credit and the government will pay the rest.
The government faced some trouble renegotiating the funds from India when the cost increased by around 121%.
The main construction work began early this year. Indian Ircon Limited is developing the rail line and the Larsen and Toubro Limited is building the Rupasa bridge following two separate deal with BR.

