Why is digging always during the monsoon?

Update : 01 Jun 2014, 07:13 PM

Utility service providers of different government agencies are carrying out excavation works on different roads in the capital in violation of city corporation rules, increasing the sufferings of residents in the process.

Officials of two city corporations in Dhaka said according to the rules, all the work should have been over by May 15 and would only resume from October so that people, especially commuters, do not suffer when it rains.

Oddly enough, city corporation and other government service providers only seem to get busy as soon as the rainy season sets in.

A number of roads and walkways in Dhaka have become unusable as different public service providers are separately excavating them. Soil, garbage, brick chips, sand and other construction materials have occupied a large part of the roads.

The DNCC has excavated Airport road in Banani, Panthapath road near Bashundhara City and several roads in Mirpur to lay pipes for a storm drain system.

The excavation work, which began in February, was part of a plan for infrastructural development and beautification of the capital ahead of the ICC T20 World Cup.

The Local Government Division is implementing the Tk115 crore project, with Tk92 crore coming from government funds and the rest from DNCC funds. On January 19, the Executive Committee of the National Economic Council (Ecnec) approved the project.

A city corporation official said the development work had to continue during monsoon because of lack of an effective plan from the top authorities and also the negligence on the part of city corporation authorities and contractors.

Brig Gen Md Abul Khair, chief engineer of DNCC, told the Dhaka Tribune: “Work began in February but could not be completed because of shortage of time.”

“Before the world cup, we only completed the beautification work, and we also temporarily suspended development work because of the sporting event,” he said, adding that work had since resumed.

“All the excavation work should have been over by May 15 but we failed to meet the deadline. We hope it would be complete by this month.”

Meanwhile, Dhaka Water Supply and Sewerage Authority (Wasa) could not finish installation of water and sewer lines in Tejgaon industrial area, Indira road, Pallabi and Dhanmondi residential area before the monsoon either.

Neither Dhaka Wasa Managing Director Taqsem A Khan nor Deputy Managing Director (operation and maintenance) SDM Kamrul Alam Chowdhury could be reached over phone.

Bangladesh Telecommunications Company Limited is also digging different roads in the city for laying optical fibre cables.

Meanwhile, city dwellers said such excavation and development work, particularly during the rainy season, leads to problems for both pedestrians and vehicles, contributing often to tailbacks in the city.

Shafiqul Islam, a resident of Banani, said: “Digging roads during the monsoon has become a common practice in the country. I do not understand why they always do it right when it is rainy season.”

“We suffer on rainy days because of this excavation. Sometimes pedestrians slip and fall into potholes,” said Rahima Begum, who lives in Green Road.

Ashoke Madhab Roy, additional secretary for the urban development wing of the Local Government Division, told the Dhaka Tribune: “We do not set the deadline for any development work. The city corporation is the authority here.”