After extending the deadline twice for relocating the tanneries in Hajaribagh to Savar, the government has decided to finish the project within three-and-half years.
In a press conference at the industries ministry Sundayday, Industries Minister Dilip Barua said, “We are trying to modernise the industry. The most important component of the project- CETP has got the final approval from Ecnec after overcoming all hurdles.”
“The project will be completed by June, 2016,” he added.
However, the construction work of the country’s first large Central Effluent Treatment Plant (CETP) will be completed within 18 months as the European Union, the leading destination of the country’s leather exports, has already warned that it will stop buying products from Bangladesh beyond 2014 if the CETP is not established in the industrial zone by then.
The second revised project proposal, which was approved by Ecnec on August 13, includes new components such as solid waste management system, sludge power generation system and sewage treatment plant to make the CETP more effective and eco-friendly.
Tannery is the second most exported item after garments in Bangladesh.
The minister requested tanners to help the government in implementing the project.
The construction of administrative buildings, police outposts, fire brigade stations, pump driver’s quarters and a pump house in the project area are complete. Also, deep tube wells, drains, culverts, water delivery pipelines, electricity lines and gas lines have been already been laid. The central water delivery system, which has a 23 million litre daily capacity, has started lifting water on a pilot basis. A sub-power station with a 10MW generation capacity has been built in the industrial area.
Moreover, a maximum of 5MW power can be generated from the sludge to operate the CETP if the project is implemented. The power can also be used for production work.
The original project cost doubled in the second revised proposal because of the delay. The project cost now stands at Tk10.78bn, whereas in 2007 the ministry had estimated the cost at Tk5.45bn in the first revised project proposal. The scheme was originally approved in 2003 with an approximate cost of Tk1.75bn. The government has decided to provide Tk2.5bn as compensation to the tanners for relocation and bear Tk6.63bn (80%) of the total project cost. However, the owners will have to pay the remaining Tk1.65bn (20%) in instalments.
The industries ministry has already allocated more than 205 plots on 200 acres of land to 155 industry units under Bangladesh Tanners Association and Bangladesh Finished Leather, Leather Goods and Footwear Exporters’ Association.
On March 11, 2011, the ministry gave the work order to build CETP and dumping yard to the Chinese contractor JLEPCL-DCL JV. The total tender value was Tk4.77bn.