Prime Minister Sheikh Hasina has inaugurated work on the Padma Bridge Rail Link Construction Project— unveiling a new era for railways in Bangladesh.
She unveiled a plaque for the groundbreaking of the Dhaka to Jessore rail link, on the Mawa side of the bridge.
Railways Minister Md Mazibul Haque briefed the prime minister about the model of the rail link project, reports BSS.
Ministers, prime minister’s advisers, parliament members, the chief of army staff, senior Awami League leaders, the project director of the Padma bridge scheme, as well as high civil and military officials were present at the occasion.
A munajat was offered seeking continued peace, progress, and development of Bangladesh—as well as for the eternal peace of Father of the Nation Bangabandhu Sheikh Mujibur Rahman and August 15 martyrs.
The first phase of the construction project will establish a rail link between Mawa and Bhanga, via Janjira, and Shibchar—via the Padma Multipurpose Bridge.
It will connect: Dhaka, Narayanganj, Munshiganj, Shariatpur, Madaripur, Faridpur, Gopalganj, Narail and Jessore.
China Railway Group Limited, a Chinese government-nominated contractor, is implementing the project under the China G2G system.
A loan agreement of $2667.94m was signed with Chinese Exim Bank for this purpose.
Under the project, a 23km ballast-less elevated viaduct rail line will be constructed.
On the elevated viaduct, two platforms – one mainline and two loop lines – will be constructed and elevators will be installed.
The Engineering Corps of Bangladesh Army, and Bangladesh University of Engineering and Technology (Buet) are consultants on the project.
Earlier, the prime minister arrived in Mawa, from Dhaka, by an Air Force helicopter, around 11am. Sheikh Hasina first unveiled a plaque of the progress of the work of the 6.15km bridge on the Mawa side.
She also inaugurated the 1300m permanent river bank protection work in the Mawa-Kandipara-Jasholdia area.
The estimated cost of the Padma Bridge Project is Tk30,193.39 crore. Of the amount, Tk12,972.46-crore has thus far been spent.
Officials informed the premier that the implementation of work on the bridge is satisfactory and its overall progress is 60%. The physical progress of the main bridge is 70%.
With setting up the fifth span, they said 750m of the bridge’s main structure has become visible.
Vehicles will drive on the upper deck of the bridge while trains will run on its lower deck, officials said.
They said 19 southern districts will be directly connected to Dhaka by road and rail—once the bridge is completed.
The expressway construction project of the Dhaka (Jatrabari)-Mawa and Pachchar-Bhanga Highway was approved by the Ecnec on May 3, 2016.
The 51km highway was upgraded to the four lanes, from two lanes, as per a modern traffic design, and Tk6,852.29-crore was spent to implement the scheme.
There is a 5.5m-wide separate lane on both sides of the highway for slow-moving vehicles and a five-meter wide median in the middle of the highway.
Arrangements have been made for the construction of a metro rail and elevated expressway on this median.
Additionally the project boasts: there are 54 culverts, 20 underpasses, four big bridges, 25 small bridges, five flyovers, two interchanges, and four railway overpasses.
Due to the addition of these facilities, the highway has been turned into an expressway.
Prime Minister Sheikh Hasina later addressed a “sudhi samabesh” (civic rally) at Mawa Golchattar—adjacent to Mawa Toll Plaza.
She will visit the Janzira side of the Padma Bridge and unveil the plaque for the progress work of the bridge, there, in the afternoon.