Gross irregularities in Naikkhyangchhari road repair work

The repair works of Naikkhyangchhari-Sonaichhari road in Bandarban has been plagued by gross corruption and irregularities. The residents of the nearby areas complained that the construction company had been using poor materials to embezzle a large sum of money. The government officials concerned, however, refuted the allegations as baseless. The Tk1 crore project of repairing the 5km-long Naikkhyangchhari-Sonaichhari road was first assigned to Milton Traders, a construction company owned by local contractor Milton Chakma. Later another contractor named Abu Bakar had bought the work order from Milton Traders. Abu Bakar has been using the least quality materials to line his pocket. According to the upazila engineering department, the work started in the late April this year and is supposed to be completed by the end of June. So far, repair of 3km-stretch has been completed.

A driver named Abdur Rouf said: “The road will be full of potholes very soon. The contractor has used brick chips of poor quality and just spread sand on the bitumen layer instead of using roller.”

The road carpeting was supposed to be 12mm thick but it was actually only 4-5mm in reality DHAKA TRIBUNE The Dhaka Tribune correspondent has found in investigation that even though the contractor was supposed to fill the existing potholes with soil at a cost of Tk40,000, no soil was used during the repair works at all. The drain alongside the road was supposed to be three-foot wide but it was found to be 2.5 feet. On the other hand, the road carpeting was supposed to be 12mm thick while it was actually only 4-5mm in reality. Moreover, the bitumen used for carpeting was supposed to be of 60-70 grade, but the contractor has used diluted and low quality bitumen. Due to the irregularities, the surface has already developed curves in different places of the road. Rezaul Karim, assistant engineer of LGED’s Naikkhyangchhari office who is supervising the repair work, claimed that he had advised the contractor to maintain standard. “If we find any irregularities, we will take steps against the firm,” he told the Dhaka tribune. However, Naikkhyangchhari Upazila Engineer Shahidul Islam claimed that the people had been questioning the quality of work due to their ignorance. “No low quality materials have been used during the repair works,” he added.