The history of nuclear power in Bangladesh dates back to early 1960s even though no nuclear power reactor has been built as yet. A site was selected at Rooppur in Pabna and necessary land for the construction of the plant was acquired in 1962.
All the gas fields of Bangladesh being situated in the eastern zone, the western zone of Bangladesh where Rooppur is situated had no indigenous energy resources. There was no interconnector between the electrical grids of the eastern and the western zones before independence. That was the reason for selecting the site for the first nuclear plant in the western zone of Bangladesh.
There were three serious offers to build the Rooppur nuclear plant prior to our independence. One was from Westinghouse of USA for a 60MWe (megawatt electric) pressurised water reactor (PWR), one from V/O Technopromexport of the former USSR for a 400MWe PWR (VVER) and another for a 200 MWe PWR from WENESE, a licencee of Westinghouse stationed in Belgium.
The Westinghouse offer was rejected by the then Pakistan government on the ground of high interest rate of financing even though it was one of the best offers we had at that time. The USSR offer was not considered because the size of the reactor was too large considering the small size of the isolated western grid. There were also some concerns about the safety of the proposed VVER reactor without any containment building, an essential safety feature of a nuclear power reactor.
We made considerable progress in our negotiations with the Belgians to the extent that the contract for the construction of plant was due to be signed after the general election of 1970. The Belgians backed out from the deal after war had broken out in Bangladesh following the general election.
The demand and supply situation of the power system changed significantly in Bangladesh soon after independence as many industries became inoperative, partly due to the damages caused by the war of independence and partly due to the departure of the Pakistani industrialists. Consequently, the demand for power dropped considerably.
It was, therefore, difficult to justify the introduction of nuclear power in 1970s as we had more generating capacity than required. A few attempts were made later by the Bangladesh Atomic Energy Commission (BAEC) for building the Rooppur nuclear power plant but none was successful. In the meantime, several feasibility studies had been made which again justified the construction of the nuclear power plant at Rooppur due to the paucity of energy resources.
Natural gas, which once generated more than 80% of our electricity, is depleting rapidly. No new gas field with any significant deposits was discovered in recent years. The present gas reserve is estimated to be 6.9Tcf (trillion cubic feet) which can hardly sustain generation of more than 3,000MW of electricity. These gas reserves are likely to be exhausted in 10 to 15 years unless new gas fields are found.
We have several coal deposits with a total reserve of 3.3Gt (billion metric tonnes). They are situated deep underground, making mining difficult, expensive and risky. There are also some environmental issues associated with the extraction and burning of coal for power generation.
At present, coal is mined only from one coalfield in Barapukuria. A 250MWe coal-fired power plant has been in operation there since 2006. Both the power plant and the mining of coal encountered numerous problems since their inceptions.
The exploration of coal from other coalfields is being hampered without a national coal policy. Speaking hypothetically, even if all the coalfields are explored, they can hardly generate 15,000MWe when in full production. We should remember that it would take 10-12 years to start commercial extraction once we decide to mine a coalfield.
Full production of coal may, therefore, take decades. The government has, however, decided to build two large power plants close to the coastal belt using imported coal. Concerns have been expressed by experts about the environmental impact of the coal-fired plants on the surrounding areas, particularly the mangroves of the Sundarbans.
While our natural gas is being depleted and the extraction of coal remains uncertain, the demand for electrical power has been rising steadily. According to the Master Plan of the Bangladesh Power Development Board (BPDB), the power demand will exceed 10,000 MW by 2015, 17,000 MW by 2020 and 25,000 MW by 2025. Under such circumstances how can we meet the power demand beyond 2020? Is nuclear power an option?
Even after the Chernobyl and Fukushima nuclear accidents, nuclear power remains a viable alternative to conventional power. It may be mentioned here that the causes of the two major nuclear accidents are now well understood and nuclear reactor design has undergone numerous modifications to make them safer.
Modern generation-3 nuclear reactors are much safer than generation-2 reactors. Nuclear power is also economically competitive compared with conventional power based on imported fuel. Environmentally, nuclear power is the cleanest form of energy, as it does not generate greenhouse gases.
Today 437 nuclear power reactors with a combined generating capacity of over 372,000MWe are operating in 31 countries, producing 13.5% of the world’s electricity. It is true that Japan and some countries in Europe decided to phase out nuclear power. Their decisions are mostly based on political considerations. Many countries in Asia, the Middle East and East Europe are building new nuclear power plants.
Alternative energy sources like imported liquid fuel, imported coal and renewable energy being too expensive, nuclear power has good prospects in Bangladesh provided we prepare ourselves to build and operate the nuclear plants safely. As a matter of fact, nuclear power can supply up to 25% of the peak demand i.e. half of the base load in Bangladesh. Bangladesh should, however, plan for a series of nuclear power plants, not just for one or two plants.
Under such circumstances, Bangladesh and Russia signed a memorandum of understanding (MoU) in May 2009 for exchanging nuclear technology and construction of nuclear power plants in Bangladesh. One year later, the two countries signed an agreement of cooperation for design, construction and operation of nuclear reactors. The agreement also covers nuclear fuel supply, return of the spent nuclear fuel, nuclear waste management and personnel training.
In November 2011, the government of Bangladesh inked an agreement with Russia to set up a two-unit nuclear power plant at Rooppur with a capacity of 1,000MW each. The deal does not include any time schedule or the cost of the project.
In February 2012, the Ministry of Science and Technology signed an agreement with Russia for advisory support on nuclear regulation, licensing and supervision. Bangladesh Atomic Energy Regulatory Bill was passed in 2012 and the regulatory authority (BAERA) was formed recently. In January 2013, Bangladesh and Russia signed a $500m loan agreement to cover the costs of a feasibility study, plant design, infrastructure development and training of the plant’s personnel.
On April 2, the Executive Committee of the National Economic Council (ECNEC) approved the first phase of a 2,000MW nuclear power project in Rooppur at a cost of Tk5,242crore without specifying the total cost of the project.
BAEC recently signed an agreement with NIAEP-ASE, the Russian state-controlled nuclear power plant design and construction company, to conduct a technical and economic feasibility study, an environment impact assessment study, site engineering survey plus several other studies for the Rooppur nuclear power project (RNPP).
Even though the government intends to go ahead with the nuclear project on a fast track, serious doubts have been expressed by experts about the lack of properly trained manpower, cost of the project, suitability of the Rooppur site, availability of cooling water for the plant, safety of the VVER-1000 nuclear reactors, nuclear disaster management and the expenditure of a huge sum of money for the project before any feasibility study and environmental impact assessment.
Soon after independence, Bangladesh inherited a corps of very highly qualified nuclear scientists and engineers. Among them, there were about 40 nuclear engineers, many of whom worked in very senior positions in the Karachi Nuclear Power Plant and the Nuclear Power Division of the Pakistan Atomic Energy Commission in Karachi. Some of the BAEC engineers later went abroad to build nuclear reactors, to teach nuclear engineering courses at universities or work in the nuclear industry or the International Atomic Energy Agency in Vienna.
Following the retirement of remaining nuclear engineers, there was hardly any recruitment and training of engineers by BAEC for implementation of a nuclear power programme. The BAEC recruited engineers mostly for operation of the research reactor at the Atomic Energy Research Establishment (AERE) at Savar and for maintenance of the BAEC establishments.
Without any nuclear power programme, BAEC grew up basically as a research organisation. It has a large number of research scientists but not properly trained engineers to build, regulate and operate nuclear power plants. Even the director-general of the International Atomic Energy Agency (IAEA), Yukiya Amano, recently commented that “Bangladesh lacks in manpower.”
Although negotiations with the Russians started four years ago, serious lapses were noticed in the management of the Rooppur nuclear power project. There were no attempts to recruit and train engineers for the management of the project and for nuclear regulation.
The project management team is the key organisation that supervises all the project activities starting from planning up to handing over the completed plant to the operation team. The function of a nuclear regulatory body is to protect public health and the environment from uses of nuclear facilities and materials.
A competent management team with engineers having experience of construction/operation of nuclear/conventional power plants and a proper nuclear regulatory body are essential prerequisites for initiation of a nuclear power programme.
It takes 3-5 years to train engineers for the project management team and also for the regulatory body. Recruitment and training of engineers for the operation and maintenance (O&M) teams may start 2-3 years prior to the signing of the contract for the construction of the plant.
It took four years to sign the agreement for the preparation of the feasibility study of the project where as it should have been completed two years ago. The feasibility report is now under preparation by a subsidiary company of the likely supplier of the nuclear power plant.
Needless to say the study will lose much of its credibility, as its findings, particularly on the cost of the project and safety of the nuclear plant, are likely to be biased in favour of its parent company. For an impartial appraisal of the feasibility of the project, it was necessary to employ an independent and reputed consultant, preferably from a western country.
Contrary to normal procedures, the Russians granted a loan of $500m (Tk4,000 crores) to Bangladesh and the ECNEC approved the first phase of a 2,000MWe nuclear power project at a cost of Tk5,242crores before the feasibility study and without knowing the total cost of the project.
Such anomalies are likely to occur in the future also unless the management of the project is handed over to a more competent body like a separate nuclear power corporation which will own, plan, build and operate all nuclear power plants in Bangladesh, like in India and many other countries.
It may be mentioned here that nuclear power plants around the world are owned and operated by either electric utilities or corporations, not by Atomic Energy Commission except in Pakistan. However, unlike Bangladesh, Pakistan has a strong group of trained nuclear engineers.
The cost of a 1,000MWe nuclear power reactor is estimated by the government at $1.5-2bn (Tk12,000-16,000 cores) even though the current market price of similar Russian reactors is $4bn (Tk32,000 crores). Two 1,000MWe reactors at Rooppur are, therefore, likely to cost about $8bn (Tk64,000 crores). Will it be wise to spend Tk5,242crores, approved by ECNEC, for such a large project before the establishment of its feasibility?
The site at Rooppur was selected for a 50-60MWe nuclear plant 50 years ago. The proposed size of the plant has increased to 2,000MWe while the flow of water in the Ganges decreased significantly due to the construction of the Farakka Barrage upstream in India. The population around the site has also more than doubled during this period.
A re-evaluation of the Rooppur site is, therefore, essential to ensure the availability of cooling water for the reactors, transportation of heavy equipment to the site through the Ganges, safety of the plant against any seismic activity or liquefaction of the soil during the monsoon periods and evacuation of an estimated three million people to a safe zone in case of a nuclear accident.
Concerns have also been expressed about the safety of the VVER-1000 reactors that have been proposed for Rooppur. Contracts for a total of 11 VVER-1000 reactors (2 in Hungary, 3 in Ukraine, 4 in Germany and 2 in the Czech Republic) were cancelled for failure to meet the European safety standards. Construction of two similar reactors in Balakovo in Russia and one in Iran was also suspended.
The Atomic Energy Regulatory Board (AERB) of India recommended 17 safety-related modifications for the VVER-1000 reactors now under construction in Kudankulam in Tamil Nadu. The Tianwan nuclear power plant in China incorporates Russian VVER-1000 reactors with a digital instrumentation & control (I&C) system supplied by a western consortium to improve safety and reliability.
It may be mentioned that customised designs usually escalate cost and cause delays in construction schedules. It is claimed that VVER-1200 reactors, producing 1200MWe power, have higher efficiency (36.56%), longer core life (50-60), lower per unit capital costs, shorter period of construction (54 months) and enhanced safety features with a core damage frequency (CDF) of 1×10-7.
VVER-1200 reactors are designed to meet the safety standards of both USNRC and European Utilities’ Requirements (EUR) and are under construction in Leningrad II and Novovoronezh II power plants in Russia.
With the projected peak power demand of over 20,000 MW, it may be possible to integrate 1200MWe reactors into the grid by 2022 without any additional risks of system instability. It is, therefore, strongly recommended that we consider VVER-1200 reactors, instead of VVER-1000 reactors, for Rooppur and other sites in Bangladesh.
The essential steps before we proceed for a nuclear power programme are: (i) formation of a separate nuclear power authority, (ii) formation of a competent project management team (iii) re-constitution of a strong and independent nuclear regulatory body, and (iv) building a competent O&M team.
To build necessary manpower, we can take the following steps: (i) recruit experienced nuclear engineers of Bangladeshi origin from abroad, if available, (ii) recruit local engineers who are experienced in construction and/or operation of conventional power plants and train them in nuclear engineering, (iii) train the present BAEC engineers in construction and operation of nuclear or conventional power plants, and (iv) recruit top-grade fresh graduate engineers and train them in nuclear engineering.
I must stress here that there is absolutely no reason to rush to build a nuclear power plant until we are fully prepared with the required and trained manpower. If we do, we shall continue to make mistakes like we have been making. Any experimentation in the construction of nuclear power reactors will be too risky and too expensive.
We waited for 50 years for nuclear power. What is wrong in waiting for a couple years more and build the manpower first? Many professionals have been suggesting the abandonment of the Rooppur nuclear power project in view of the shortage of manpower and concerns about safety.
If our engineers could build and operate nuclear power plants abroad, there is no reason why they cannot do it in Bangladesh. I believe we can build and operate nuclear power plants safely provided we first build the required manpower, buy the nuclear reactors with state-of-art safety features and religiously apply the nuclear safety regulations.