A 100-kilovolt (KV) electric transformer being used by the Power Development Board (PDB) has been placed right in the middle of a busy area in Kishoreganj municipality over the last four months, posing a serious threat to the locals.
The high voltage transformer, connected to the main lines of the national grid with heavy metal wires, is set up in the middle of a road in Ukilpara area of the municipality.
Visiting the spot on Thursday, this correspondent witnessed hundreds of people walking up to the transformer to touch its iron net enclosure, something that can cause a serious accident any time.
The transformer receives 100kv electricity from the national grid’s supply line and later it is converted into 440-volt after undergoing process and supplying it to consumers, the PDB sources said.
If anyone touches any part of the risky transformer out of curiosity, he might be electrocuted and sparks might lead to a devastating fire, they assumed.
As per the PDB rule, such a transformer must be installed on electric poles, at least 10 feet above the ground with special protective arrangements.
The transformer had broken down four months ago, and has been replaced with another one installed on a pole, locals said.
Since then, the PDB employees did not repair the transformer, putting lives of thousands of people at risk.
Locals said they were worried as the new transformer often send out sparks of electricity during the rainy season.
Every day, thousands of people, including school-going students and patients, go along the road, said Elius Uddin, a resident of the area.
“I am especially anxious for school children who can touch the risky transformer’s cage as they are not aware of its danger,” said school teacher Shamima Akter, also a resident of the area.
Councilor of ward no 3 Hanif Uddin Ahmed Ranak said he had informed the PDB officials about the matter, but no results had come yet.
PDB officials said they had installed the transformer on the ground as a temporary basis, as the earlier transformer had been stolen from the poles around four months ago.
“We will bring a new transformer from the Dhaka divisional office immediately,” said an official preferring to be unnamed.
Ubaidul Islam, executive engineer of the PDB Kishoreganj, said: “I have joined here around three months back, but I have not been informed about the matter.