The Bangladesh Water Development Board (WDB) started dredging the Jamuna river channel to protect Sirajganj town from erosion, spending around Tk100 crore.
According to sources, the dredging will start from Shoilabari of Sirajganj Sadarupazila to two protection embankments and from Mollabari crossbar embankment to Bangabandhu Bridge through the project ‘Capital dredging river system in Bangladesh’.
The sources said the step was taken in the name of maintenance. The work was not effective in the last two years.
The WDB sources said the authorities started the work in 2011-12 fiscal year spending Tk 1,028 crore in order to protect Bangabandhu Bridge and Sirajganj town. The dredging was done from Shoilabari to Bangabandhu Bridge during last two years spending Tk 4,00crore.
But the steps failed as a large shoal emerged close to the dam at the eastern side of the city.
Later, the authorities started dredging across one kilometre of the river.
Tofayel Ahmed, chief of WDB taskforce said, unplanned dredging of the river brought no results.
He added it was important to remove sands nearby Sirajganj town protection embankment rather than digging near the cross dam. The embankment collapsed due to floods.
Ataur Rahman, consultant of the project said although the project failed during last two years, the work started for the third time costing Tk 100 crore.