Experts and stakeholders have expressed doubts about the benefits of a government move to finalise a new model production sharing contract (PSC) to lease onshore hydrocarbons blocks to international oil companies (IOCs).
The new PSC is set to be finalised this year to clear the way for the government to solicit tenders to explore oil and gas.
According to relevant laws, Petrobangla has the right to sign agreements with IOCs for the purpose of hydrocarbon operations. The state-owned oil company’s major activities include organising and supervising the PSCs signed with IOCs.
However, industry analysts have voiced concerns over the drilling of 41 exploratory and development wells with state funds in several hydrocarbon structures before finalising the PSC.
Speaking to the Dhaka Tribune, Prof M Tamim of the Bangladesh University of Engineering and Technology said the new PSC with foreign companies is unlikely to be a meaningful one, as the government is already drilling around 41 wells with its own funds.
“We should rethink whether there is a need for a new model PSC. If the PSC is to be signed, then tenders should be floated under the PSC for some of the 41 wells,” he said.
On behalf of the government, Petrobangla leases oil and gas wells to IOCs for exploration. There are 22 onshore blocks of hydrocarbons in the country. Currently, US-based Chevron is exploring blocks 12, 13 and 14. Block 9 has been leased out to Singapore-based KrisEnergy.
Bangladesh Petroleum Exploration and Production Company Ltd (Bapex) has, too, decided to drill 28 exploratory and development wells in some of the oil and gas structures under seven projects – dubbed as Rupkolpo 7 (Vision 7). The projects are scheduled to be completed by December of next year.
Even though state-owned Bapex has the capacity to implement exploration projects, the government selected three foreign oil companies for drilling for hydrocarbons in 13 onshore wells.
The companies – Russia-based Gazprom, Azerbaijan-based SOCAR AQS LLC, and Sinopec International Petroleum Service Corporation in China – were selected under the Speedy Supply of Power and Energy (Special Provision) Act 2010.
Bapex has already finished negotiations with the companies and is set to sign deals with them.
It would cost only Tk80 crore if Bapex drills the wells. But the costs may shoot up to Tk200 crore per well if drilled by a foreign company.
Earlier, Gazprom won an exploration project without bidding for it. The company dug 15 wells between 2012 and 2016, but failed to extract gas as targeted.
Gazprom is currently drilling two onshore wells (Shahbazpur North and Shahbazpur East), costing nearly double what Bapex would have spent, according to sources.
Under the new project, Gazprom will, however, drill five wells (Mubarakpur 2, Srikail North 1, Shrikail East 1, Sunetra 2 and Madan 1), targeting a depth of 5,000-5,500m.
On the other hand, Azerbaijan-based SOCAR, which will be working for the first time in Bangladesh if the deal is finalised, will drill four wells (Begumganj 4, Semutang South 1, Madarganj 1 and Shariatpur 1), targeting a depth of 3,000-4,000m. And, Sinopec will drill four wells (Hararganj 1, Batchia 1, Patharia West 1 and Dupitila 1) at a depth of 3,500m.
When asked, Petrobangla Chairman Abul Mansur Md Faizullah declined to make any comment on whether the new model PSC would be fruitful.