35th span of Padma Bridge installed

There are plans to install the remaining spans by December 10

Update : 31 Oct 2020, 05:50 PM

The 35th span of the Padma Bridge has been installed, bringing a total of 5.25 kilometres of the structure into view.

The span was installed on pillars eight and nine at Mawa point at around 2:45pm on Saturday, confirmed Dewan Md Abdul Quader, project manager (main bridge) and executive engineer.

The next span will be installed on November 4 or 5, he said.

With the installation of the 35th span, only six more spans remain to be installed as the total number of spans is 41.

Engineers said the span-installation work gained momentum in October after being closed for the last four months due to rains. Four spans were installed this month and the previous span was installed on October 25.

There are plans to install the remaining six spans by December 10.

Construction of the 6.15-kilometer bridge began in December 2014 and is expected to be completed in June 2021, although project officials said it may take extra time.

Even if the installation of the spans is completed in December, there is still more work to be done including the installation of slabs, gas connection, and rail line connection.

Some of the steel bars of the railway have been submerged due to river erosion. They either have to be picked up, or new ones have to be brought.

For all these reasons, it will take some extra time to complete the bridge.

The construction of the main bridge is being done by Chinese contractor China Railway Major Bridge Engineering Group Co Ltd and river management is being done by Sinohydro Corporation, another Chinese company. The connecting roads have been constructed by Abdul Monem Ltd of Bangladesh.