The Appellate Division of the Supreme Court yesterday disposed of the matter of earth-filling and construction of jetties on the Meghna River at Ashuganj after the government gave undertaking that they would protect the river from encroachment.
The five-member bench headed by Chief Justice Md Muzammel Hossain passed the order on appeals of the government and Ashuganj Power Station Company Limited.
On March 13, the apex court in an order suspended the earth-filling and setting up of the jetties.
On February 13, the High Court bench led by Justice Salma Masud Chowdhury directed the authorities concerned to remove the construction materials stored at the site within seven days and take measures to prevent anyone from encroaching the river. The court gave the government four weeks to submit a compliance report before it. It also ordered the law enforcers to take proper legal action against the encroachers.
Later, the order was stayed by the Chamber Judge of the Appellate Division in response to a plea of Ashuganj Power Station Company Limited.
After a petition of the Human Rights and Peace for Bangladesh, the full bench of the apex court gave a status quo order on March 13. After the government’s undertaking, the matter was disposed of yesterday.
Lawyer Manzill Murshid for the petitioner claimed that local leaders from both the Awami League and the BNP had reportedly been occupying the land along Meghna River and trying to construct jetties.