Applicants kept waiting: 150,000 Domestic: 120,000 Illegal household connections: 58,000 Gas needed for domestic: 22mmcfd
Officials of gas distribution companies told Dhaka Tribune it would take over two years to finish providing new connections to households that have already applied for lines.
Their response follows the government’s announcement on Tuesday that they would be lifting the embargo on giving out household gas connections soon.
The distributors cited manpower shortage, lack of capacity to handle equipment as the key reason for the delay and added that new applications would also come in during the period, adding to the existing backlog of applications.
Over 120,000 applications for household lines are currently pending at the five distribution companies. These have accumulated for over two years after the government suspended giving residential lines in 2010 following the gas crisis.
“As giving new connections was suspended for around three years, we have no service materials to give out new lines including gas service tee, elbow, pipe, regulator and gas riser,” Pashchimanchal Gas Company Limited Managaing Director Md Ali Hossain said yesterday.
“We will have to purchase them and after that we can give out new connections to 15 households per day at best,” he added.
Md Nowshad Ali, the acting MD of Titas Gas Transmission and Distribution Company Limited, the highest sellers of gas amongst all the distributors, told Dhaka Tribune: “We can provide 70 to 100 connections in a day.”
The average total daily capacity of gas distributors to provide new lines stand at around 100-120 connections. It would take over two years to address the 120,000 pending applications.
Energy Division Secretary Md Mozammel Haque Khan told reporters on Tuesday there are 58,000 illegal residential connections and that they would be legalised by collecting fees. He added that around 22mmcfd gas would be required to cover all the new connections including the illegal ones and that new lines would only be given where distribution lines are already available.
At present, only five distributors supply gas through pipelines across the country. Titas holds 63% stake of gas sales, Bakhrabad Gas Systems Limited hold 14%, Karnaphuli Gas Distribution Company Limited 11%, Jalalabad Gas Transmission And Distribution Limited 8% and Pashchimanchal 4%.
BNP lawmaker Mahbub Uddin Khokon, member of Standing Committee on Ministry of Power, Energy and Mineral Resources, alleged that prime minister’s energy adviser Tawfiq-E-Elahi Chowdhury, state minister for power Muhammad Enamul Haque, and former energy secretary Mohammed Mezbah Uddin are all tied to the illegal connection supply and would be brought to book.
A Petrobangla official, requesting anonymity, told the Dhaka Tribune that they could not account for roughly Tk5bn extra deposits in their bank accounts, which was made against the illegal connections. The amount had accumulated over the years as those who took the illegal lines paid their bills.
Mozammel told the Dhaka Tribune it has been decided that only household and commercial applicants will be given connections; CNG stations and tea estates will have to wait.
Federation of Bangladesh Chambers of Commerce and Industry (FBCCI) Director Shahedul Islam Helal said that the government has to consider giving out industrial gas connection as the sector is being seriously affected. He also advocated cancelling the high power committee made to scrutinise applications and give connections on massive scale.
On April 16, the High Court withdrew its November 8, 2012 order that barred the government from distributing new lines due to supply shortage. The government stopped giving new gas connections for residential purposes on July 13, 2010 and for commercial, power plants, fertiliser and industrial purposes since July 21, 2009 citing supply shortage. It then issued a notification in this regard and said new gas connections would be given if the production reaches 2,200mmcfd.
However, the Petrobangla, currently faces a 750mmcfd shortage against the daily demand of around 3,000mmcf.