Two-thirds work remains incomplete in Barisal University campus

Update : 21 Jul 2013, 06:12 AM

More than two-thirds of the construction of Barisal University’s permanent campus is yet to be completed, though the deadline has already passed.

Classes of the university were inaugurated by the education minister on January 24, 2012 on its Zilla School campus in the city.

A slow pace of construction by the contractors and legal complexities in land acquisition forced Barisal University (BU) authorities to hold classes and perform administrative activities in a single building on the temporary campus.

The foundation of the university’s permanent campus, the only public university in the division and the 33rd public university in the country, was laid by Prime Minister Sheikh Hasina on February 22, 2011 at Karnakathi on the eastern bank of the Kirtonkhola river in the district’s sadar upazila.

After visiting the BU permanent campus at Karnakathi, it was found that not only was the construction of all seven buildings on the 20-hectare land of the BU campus incomplete, the construction of three of the buildings had yet to start.

All work orders for construction were given on January 11, 2012, and the deadline for construction was July 11, 2013.

BU office sources said tenders for the construction project at a cost of Tk577.6m were called in the end of 2011.

The project includes construction of four five-storied academic and administrative buildings and three student dormitories.

At present 1,103 students in 15 subjects under five faculties are studying at BU and 40 teachers, 24 officials and 78 staff and employees have been appointed.

In the current academic session, more 1,050 students will be enrolled, BU sources said.

Messrs Mahfuz Khan, Mudasser Ali Mallik, Gulzar Enterprise and Aman Traders received work orders on January 11, 2012 for constructing the four five-storied buildings.

About 40% of the construction of one building, 50% of another one, and 65% of remaining two, is yet to be completed.

However, the contractors already collected Tk110m (43% of total estimated cost) as running bill.

Shafikul Alam Gulzar of Messrs Gulzar Enterprise said they have to construct concrete slabs under the foundations of the building and it will require a huge amount of earth work, which is time-consuming.

On the other hand, construction bids for two male and one female five-storied residential hall at the cost of Tk322.6m went to the first three of the four contractors mentioned before.

However, until the time of this report, only 15% of construction including piling work of these three buildings was completed, but 14% of the running bill worth Tk45m had already been collected by the contractors.

Shafikul Alam Gulzar of Messrs Gulzar Enterprise claimed that construction was stalled because of legal problems in land acquisition.

Abul Bashar, executive engineer of education engineering department, acknowledging the slow pace of construction of the BU campus, said legal problems in land acquisition caused the delay.

Prof Dr Harunor Rashid Khan, vice-chancellor of BU, said they wanted to shift from the temporary campus to the permanent one by December 13 of this year.

A letter had already been sent to the contractors to speed up and complete the construction work by that time, said Bahauddin Golap, assistant registrar of the university.