Dhaka’s waterlogging worsens despite massive spending

Update : 15 Oct 2022, 04:39 PM

Despite spending millions of taka in public funds, the waterlogging situation in Dhaka is not improving due to poorly coordinated action and the absence of a long-term plan to deal with it, experts have said.

One example of ineffective action by the authorities is the installation of a new drainage pipe under Dhanmondi road 27 by the Dhaka South City Corporation (DSCC). The pipe was installed at a cost of Tk20.49 crore earlier this year, despite there being two existing drains already.

The new pipeline has rainwater go into the main pipeline under Satmasjid road, which then drains it into the Katasur canal. However, this has not helped roll back the waterlogging as the main line itself regularly becomes clogged due to a lack of maintenance and the dumping of garbage in the drains.

The DSCC cleaned the drain during the last monsoon, but a part of the drain is under the Dhaka North City Corporation (DNCC). Due to a lack of coordination between the two city corporations, that part has remained clogged, and the benefits of the new pipeline were not felt by residents of the area.

Shafiqul Islam, a resident of Lalmatia, said: “I have seen the construction of drains on this road three times in a decade. Every time I hear that the problem will be solved, but public sufferings in the monsoon remain the same.”

Dhaka Wasa and DSCC have spent Tk50.46crore since 1991 to construct three pipelines for a 1km area between Rapa Plaza and Shankar. 

“Installing new pipelines is not a solution without cleaning them regularly. If the DSCC and DNCC simultaneously do not maintain the drains properly, people will not get relief from waterlogging,” said engineer AKM Shahid Uddin, director of Dhaka Wasa.

The government handed over the responsibility of maintaining drains and canals to the Dhaka city corporations in December 2020 as Dhaka Wasa had failed to solve the waterlogging problem.

“Maintenance is cheaper than installing new pipelines, but Dhaka Wasa has always focused on new projects to eliminate waterlogging,” said Iqbal Habib, a renowned architect and urban planner.

“Now, city corporations are also focusing on new projects rather than cleaning the drain, as implementing a new project creates an opportunity for officials to take financial advantage of contractors,” he added.

Dhaka Tribune has found inconsistencies in the implementation of the one kilometre drain under Dhanmondi road 27. DSCC floated a tender to construct the drain on September 23, 2019, and one firm alone participated in the process. 

The DSCC issued a work order to the company instead of re-tendering. In addition, the type of work was changed even after the signing of the purchase agreement. 

Initially, it was planned for the drain to be an RCC type, but later a concrete pipeline was installed.

When contacted, DSCC Superintendent Engineer Md Khairul Baker declined to comment on the inconsistency or the reason for the change in plans.

He said: “The installation of a third pipeline is logical, but the people will not benefit until drain cleaning activities are coordinated with the DNCC.”

Khairul, who is also the key supervisor of the project, said more projects were going to be taken up in an attempt to solve the waterlogging problem.

Throwing money at the problem

Dhaka WASA undertook the Tk146.59 crore Capital Waterlogging Elimination Project in 2001. The project ended in 2011 after Tk203 crore had been spent, but the impact on water drainage remained negligible. 

The Implementation Monitoring and Evaluation Division (IMED) sharply criticized the project, filing an evaluation report that said all the components had not been implemented in line with the plan.

Even though the project was deemed ineffective by IMED, Dhaka Wasa implemented the second phase of the same project in 2013 at a cost of Tk248 crore. However, the waterlogging problem remained.

Apart from this project, the DSCC and DNCC jointly spent Tk154 crore between 2011 to 2013. Dhaka Wasa, DSCC and DNCC spent more than Tk400 crore from 2011-2013. 

Increasing the budget, the two city corporations spent Tk294 crore in the 2019-20 fiscal year to improve the drainage network. However, alongside the increase in the budget, the number of areas prone to waterlogging also increased.

According to documents of the two city corporations, the number of major hotspots of waterlogging is now 48, as compared to below 25 in 2018.    

To eliminate waterlogging from 13 major points, including Dhanmondi, Jigatola, Hazaribagh, Mohammadpur and Mirpur, Dhaka Wasa executed another project at a cost of Tk550 crore last year. However, visits to the areas in June and July revealed that they still were inundated with water on rainy days.

Meanwhile, the three major agencies spent Tk1,278 crore from 2018-2020. The authorities spent Tk862.91 crore alone in the 2019-2020 fiscal year. Compared with the 2012-13 fiscal year, expenditure on improving the drainage system increased five-fold. 

Both city corporations have been laying emphasis in their budgets more on eliminating waterlogging since they were given responsibility of handling the drainage system last year.

"We have already initiated activities worth Tk103 crore to alleviate waterlogging from Dhaka,” said DSCC Mayor Barrister Sheikh Taposh.

“We have also taken up a project at a cost of Tk978 crore for improving drains and canals under DSCC to eliminate waterlogging, as it is a priority issue,” he added.     

Similarly, the DNCC has allocated Tk124 crore for developing the drainage system.

Why is the spending not working?

Experts have identified three major tasks to ensure the elimination of waterlogging: Maintain existing drains to ensure smooth water flow to canals, ensure that the canals themselves are  flowing, and pump water to the river during heavy rains.  

Unfortunately, most drains in Dhaka are clogged as people dump everything from solid waste to plastics in them. Furthermore, water pumps are often damaged when they are needed the most.

“Without maintenance of the drainage system, the authorities have been emphasizing taking up new development projects. However, a series of projects never eliminates waterlogging if they do not clean drains on time,” said Commodore Razzak (Retd).

“The authorities should strictly enforce the law so that people cannot clog the drains. A well-designed plan is also important to keep the drains functional,” said Iqbal Habib.

Both the DNCC and DSCC enthusiastically embarked on massive drives to recover and clean canals in order to eliminate waterlogging from the capital from January this year. But eliminating garbage from canals is not enough if people continue to dump waste in them.

“We have decided to take legal action against those who dump waste in the canals by identifying them through CCTV cameras. Installation of CCTV cameras on the banks of canals will start soon,” said Atiqul Islam, Mayor, DNCC.