The Public Library is set to open its doors to the public in its temporary new location on March 26 since its closure in the first week of February 2022.
The library is being shifted to its temporary location on the 12th and 13th floors of the Institute of Engineers Bangladesh building at Kakrail from its current location in Shahbagh.
Additionally, the office of the Department of Public Libraries will be shifted to the BSL building near Hotel Intercontinental.
The public library has a collection of nearly 176,000 books. However, due to space constraints, 50% of the books will be showcased to the public at the new location.
The timing of the library will remain the same from 9 am to 5 pm.
The temporary library will have all the sections on a minimum scale, including separate sections for research, reference, children corner, Bangabandhu corner, and digital section.
The new space will accommodate 250 readers at a time, almost half of the previous seating arrangement.
Altogether, the Ministry of Cultural Affairs has to spend around Tk19 lakh for both spaces per month. Of them, the temporary library will account for Tk 13 lakh.
The old public library building in Shahbagh is being renovated to give it a modern look.
The demolition of the current library is scheduled to start in the first week of April.
The Tk524 crore project will be handled by the Public Works Department of the government. The duration of this project is estimated to be till June 2024.