Despite the government’s claim that load shedding has been eliminated from the country, citizens are now facing a different kind of suffering – several rounds of daily “power interruptions” ranging from 10 to 30 minutes each.
Although a new landmark of 7,000MW daily power generation was reached last Thursday, officials from different power distribution companies said the frequent interruptions happened because of nine reasons, mainly overloaded transformers, substations and worn out distribution lines.
Development work, short circuits, daily maintenance, work on giving new lines or reconnections, excess demand on consumers’ end and consumer-end problems are also reasons behind the frequent interruptions.
“There is no load shedding, but now we are facing power interruptions. People have to be patient. We are working on it,” State Minister for Power, Energy and Mineral Resources Nasrul Hamid told the Dhaka Tribune yesterday.
“We have specially tried to provide uninterrupted electricity supply to the rural areas during the T20 world cup, irrigation and summer,” he said.
According to government estimation, the country’s highest demand for 7,500MW of power would be during the ongoing world cup, Boro irrigation and summer season between March and May.
The state minister also said: “Bangladesh’s installed electricity generation capacity stands at about 11,000MW. The fuel oil- and gas-based power plants will be used to their highest capacities to meet the demand.”
Expressing hopes that load shedding will cease to exist in the country, he said: “One of the major visions of the government is to secure uninterrupted supply of electricity for all citizens within 2021 at an affordable price.”
Md Kamal Uddin, a resident of the capital’s Mohammadpur, said the load shedding crisis had eased as there was no major interruption during night, but added that there was still 10-15 minutes of power outages during day.
Nasrin Sultana, an Uttara resident, echoed Kamal and said she thought the cause of interruption was load shedding, which is an intentionally engineered power shutdown.
The country’s power generation on Thursday evening stood at 7,032MW, which fulfilled that day’s demand.
During the evenings of March 22-28, the average power generation in the country was around 6,500MW.
Five companies – Dhaka Power Distribution Company Limited (DPDC), Dhaka Electric Supply Company Limited (Desco), Rural Electrification Board (REB), West Zone Power Distribution Company Limited (WZPDCO) and Power Development Board (PDB) – currently distribute electricity to 1.4 crore consumers throughout the country with a 285,101km network.
One of the causes behind power interruptions was transformer breakdown, said DPDC Managing Director Brig Gen (retd) Md Nazrul Hasan, adding that transformers catching fire often result in supply disruption.
Five distribution companies under the Power Division have 690,257 transformers, while 135,287 (20%) of which were overloaded, according to the Power Division, while around 7% of the substations had already exceeded their capacities.
Among the power distributors, the REB has the maximum overloaded transformers, with 130,259 of its total 644,079 transformers being overloaded.
Every year, 35,000 transformers are damaged for overloading, causing losses worth Tk200 crore.
To tackle the crisis, REB chairman Brig Gen Moinuddin asked all Palli Bidyut Samity to submit reports on the reasons behind the overloading and the damage.
The REB chairman said: “We have the maximum consumers and the power supply lines are worn out. In REB areas, interruption rate is apparently higher because of lack in maintenance. We have taken some projects to solve the problem within 3-4 years.”
According to Power Division, 382 of Desco’s 5,332 transformers were overloaded, while 1,090 of the DPDC’s 9,348 transformers were also overloaded. Of the PDB’s 25,809 transformers, 3,450 were overloaded, and 106 of WZPDCO’s 5,689 transformers were overloaded.
Desco officials said several hundred kilometers of their 3,500km supply lines were in a vulnerable state.
“The DPDC has supply lines over 4,000km, of which 200km lies in dilapidated condition,” a DPDC official said.
The REB has supply lines of over 228,000 km, while most of its substations were not in a state to sustain the overload. The REB distribution lines were also quite old and there had been technical problems because of long power outages and frequent damage of transformers, said REB officials.
The WZPDCL supplies electricity to its consumers through 9,000km of distribution lines, a large portion of which was in sorry state.
Nearly 12% of PDB’s 40,000 km distribution lines were in bad shape, said PDB officials.
The DPDC and Desco supply power to the capital and its outskirts, the REB covers rural areas, and WZPDCL supplies to 21 districts in the southwestern region. The PDB supplies electricity to both rural and urban areas except Dhaka, Barisal and Khulna metropolitan areas.