Installation of waste-based power plants in Dhaka have fallen into uncertainty as the project has seen no progress even after ten months had passed since the government inked an agreement with Management Environment Finance, an Italian company, for establishing the power stations.
The government is now planning to cancel the agreement with the MEFSrl Ltd if it fails to assure the financial arrangement for the project within next March. The foreign firm has already spent 10 months of the project as it could not arrange its financial support.
Admitting that the company had failed to sum up finances to start the construction work of the power plants, Additional Secretary to the Local Government Division KM Mozammel Haque told the Dhaka Tribune last week: “We have warned them that they must start the construction work within next March 31.”
“The management of the company has assured us that they would be able to arrange finances within next March as a United Arab Emirates company and another company showed interests to invest in the project.Being satisfied with their commitment and recommendation from high officials of the government, we have extended the time. But we will be compelled to cancel the agreement if they fail again to arrange the finance by the
deadline,” he added.
Mozammel Haque, key person of the project, also added: “We can cancel the agreement anytime and we have other interested parties in this regard. But it would require more time as we had already delayed the start of the construction work. Thus, we are now waiting for them. The deadline would not be extended anymore, if they fail again.”
When contacted, none of the representativesof Management Environment Financein Bangladesh agreed to make any official comment in this regard.
An official of the company, on condition of anonymity, alleged that they failed arrange the finance as they were not provided with a sovereign guarantee from the concerned office of the government. The company officer reported that Bangladesh Bank officials did not cooperate with them in this regard.
In case of loans to multinational institutions, a loan qualified as a sovereign guaranteed one if it is backed by a member country, or by member countries in whose territory the borrower shall execute the project.
According to the agreement signed on April 18, 2013, between the local government division and MEF, the company will install two waste-based power stations at Aminbazar and Matuail waste dumping areas in Dhaka city.
The local government division officials said, it was scheduled to start the construction work of two power stations by September last year. But the company failed to do so as they could not arrange the financial support for the project within the time frame. Later, the MEF authorities applied for an extension of starting the installation works of the stations.The deadline was extended up to December first, and later up to March, though the company wanted it extended further to June this year.
According to the agreement, the investor company will loan $300million for the project. The government will provide around 43.4 acres of land on lease. The company will pay the government Tk6.944million as lease money, which would be increased by 20 percent in every five years.
The power stations will produce 10MW power in the first 18 months. The production will then be raised to 30MW by the second year, 50MW by the third year and finally produce 100MW the next year.
The Dhaka Power Distribution Company and Dhaka Electric Supply Company will purchase the produced electricity atTk8.75 per unit.
The power stations would also produce around nine million tonnes of organic fertilisers annually as supplementary product.
The investment of the company will be transferred based on “Build, Own, Operate and Transfer”method within 20 years of the beginning of the project’s operation.