The state-owned Dhaka Power Distribution Company has decided to bring all of its consumers under prepaid meters by 2018, scrapping the conventional system.
The DPDC and Bangladesh Diesel Plant (BDP) Limited, a commercial enterprise under the management of Bangladesh Army, yesterday signed a deal on the pilot project for installing prepaid meters for the first time, DPDC Managing Director Md Nazrul Hasan said.
They will install around 10.6 lakh meters for around 15 lakh consumers within 2018, aiming at stopping harassment of the consumers and ensuring 100% revenue collection in advance.
At least 962,500 single-phase pre-paid meters will be installed at a cost of Tk1,300 crore and 9,700 three-phase ones at Tk3.76 crore.
“In the pilot project, 10,000 single-phase pre-paid meters will be installed under the Azimpur Network Operation and Customer Services division. Of the meters 5,000 will be installed by May and the rest by September this year,” Nazrul Hasan said.
The areas to be brought under the pilot project are Dayra Sharif, Eden College, Salimullah orphanage, government quarters and its adjacent areas.
At the deal signing ceremony, State Minister for Power Nasrul Hamid said: “We are trying our best to save consumers from hassles of getting new connections and to reduce systems loss.
“Other distribution companies such as the Rural Electrification Board will be brought under the pre-paid meters gradually.”
A consumer will have to buy a smart card from the Network Operation and Customer Services and deposit an amount against the card; then the card will have to be inserted into the pre-paid meter’s slot to begin electricity supply.
The DPDC will establish 36 vending stations for selling and recharging these cards.
A pre-paid meter will cost a consumer Tk5,000-Tk5,500, which can be paid in monthly instalments in eight years.
Project Director Mohiuddin said it was a win-win situation for the DPDC as well as its customers as it would provide a number of benefits for both parties.
The company would give a couple of days to pay the bill for an upcoming month, but the duration of that window was yet to be decided, he said.
Upfront payments, improved cash flow, decreased non-technical
losses, lower overhead expenses and meter-tampering protection were the benefits the company would enjoy after introducing the new meters, he said.
The DPDC, which started commercial operation in the Dhaka City Corporation on July 1, 2008, has nine lakh consumers at present.
On September 7, 2005, the Dhaka Electric Supply Company Limited (Desco) introduced locally made pre-paid meter system in the capital’s Uttara Model Town, but it failed to start the main project.
Under the Desco pilot project, 14,000 meters were installed.
A group of students and teachers of Bangladesh University of Engineering and Technology developed the pre-paid meter system.