Five ADP power projects show little progress

Update : 22 Jan 2014, 07:53 PM

The planned addition of 930MW to the national grid will be delayed as there has been no progress in the implementation of five ADP power projects in the first six months of the current fiscal year.

This will eventually hamper power saving as well as service to consumers, says an official report.

The projects are: the construction of Sylhet 150MW combined cycle power plant and transmission system; prepaid metering for Chittagong south zone; the construction of Shahjibazar 330MW plant; efficient lighting initiative for Bangladesh (parts 1 and 2); and Ashuganj 450MW combined cycle plant (north).

The report of the Power Division shows that out of 56 projects eight have made only 1-5% progress, nine 6-25%, and the rest completed 25-88% of the implementation work during the period.

The Power Division also missed its ADP target set for the July-December period, according to the report released at a recent meeting.

The agencies responsible for completing the projects implemented 23.92% of the ADP allocations during the period against a target of 32.93%.

The progress rate, however, dropped 3.2% from one year ago – the implementation was 27.12% in the first half of the last fiscal year.

According to the report, the Power Division spent Tk2,094.76 crore for these ADP projects. Of the amount, the government contributed Tk1,543.96 crore (29.55%) and foreign loans and aids were Tk550.80 crore (15.6%).

Against a target of 45.21% physical implementation these projects have completed 42.48% – a 3.17% increase from the period of the last fiscal year.

The FY2013-14 budget earmarked Tk65,872 crore for total ADP, and of the amount, Tk8,756.14 crore was allocated for the Power Division.

Of the total ADP projects, the Power Development Board is implementing 22, the Rural Electrification Board 11, the Power Grid Company of Bangladesh 10, the Dhaka Power Distribution Company three, the North West Zone Power Distribution Company five, the Electricity Generation Company of Bangladesh two, and the Power Cell, West Zone Power Distribution Company and Ashuganj Power Station Company are implementing one each.

“We have been able to increase the pace of physical implementation compared to last year. But we still lack speed in the progress of financial implementation,” said Power Secretary Monwar Islam.

He expressed hope that the financial implementation would also get momentum in the next fiscal year.