Locals in the district remain vulnerable to flooding as a 2.5-kilometre flood control embankment has been damaged by the recurrent cyclones over the past four years.
The embankment was yet to be repaired though the deadline to repair it has been long over, sources said.
The damage was found at least at 10 points of the flood control dyke and around 900 meter of its concrete part had been devoured by the Jamuna River that misplaced the earth underneath the dyke.
Local administration and inhabitants expressed concern over the Water Development Board (WDB) officials’ reluctance to repair the embankment.
Even recurrent repairs to the dyke cost Tk200crore for the last couple of years have failed to control disaster.
The WDB has taken up a Tk80-crore project titled “Water Management Improvement Project” with the support of the World Bank, Nederland’s Government and the Government of Bangladesh.
The objective of the project is to fill up the bottom of the embankment with 1,23,450 cubic metres of rock to strengthen the dyke.
The rock were supposed to be imported from abroad or brought from the rock mine of Moddopara area in Dinajpur district.
Local contractor MA Munim Ltd was awarded the tender, but the company clearly fell behind the deadline.
Local and WDB sources said only one-third portion of rock was brought till yesterday which had been stored beside the dyke and only three decimal of the embankment’s bottom had been filled with the stones so far.
Although the renovation deadline had been extended to next April 30, the WDB officials were uncertain about finishing the work within the stipulated time.
Executive Engineer Sajedur Rahman, who had been recently transferred, sent a letter to the higher officials concerned, alleging that lack of manpower, equipment, experience were a bar to speeding up the project work.
Sub-divisional Engineer of WDB Rafiqul Alam Chowdhury said the WB had not entrusted BRE with the responsibility and so it was not interested in the project.
The project team leader Drubo Kumar met journalists Monday noon, but Akhtaruzzaman of the contractor company allegedly forbade him to talk anything about the renovation project.
Nurul Amin, WDB executive engineer, said: “The construction has been going on at a snail’s pace because of lack of rock. We have nothing to do in this matter.”
Water Development Board Chief of Taskforce Tofayel Ahmed said, “MA Munim Ltd has no experience of construction work. Basically, it is the contractor company for Roads and Highways department.”
The renovation had been delayed because the inexperienced company had been tasked with the responsibility, he added.