With a view to curbing non-technical system losses and provide improved services, state-owned Dhaka Power Distribution Company (DPDC) Limited will install 144,500 (out of a total 900,000) prepaid meters in six target areas of Dhaka metropolitan and Narayanganj on a pilot basis.
“Under the project, 140,000 single-phase pre-paid meters and 4,500 three-phase meters will be installed by December 2015,” AHM Mohiuddin, director of pre-payment metering project for number six NOCS (Network Operation and Customer Services) division and manager of DPDC told the Dhaka tribune on Friday.
The areas to be brought under the pilot project, are, Lalbagh, Bashabo, Maniknagar, Bangshal, Jurain and Narayanganj east.
A digital pre-paid metre would cost between Tk8,000 and Tk12,000 compared to the existing digital metres which cost Tk1,200 to Tk2,000.
“DPDC will establish 29 utility vending stations and six utility customisation centres under the project,” he said.
It is a win-win situation for the company as well as its customers as it will provide a number of benefits for both, Mohiuddin said.
“It is easy and transparent, there can be no disputes regarding bills, while customers would not face any hassles to pay bills. In addition, there would be no scope for disconnections or reconnections; no minimum charges will be applicable for the meters.”
The company would give couple of days to pay the bill for an upcoming month, but the duration of that window is yet to be decided, the project director said.
Meanwhile, upfront payments, improved cash flow, decreased non-technical losses, lower overhead expenses and metre tampering protection were the benefits the company would enjoy after introducing the new metres, he said.
“We were forced to undertake this project to avoid weak commercial management of the DPDC and minimise its non-technical losses,” the project director said.
Apart from creating problems for DPDC, the existing system also creates problems for the customers as sometime they get bills after two or three months, sources said.
On October 29, 2013 Executive Committee of National Economic Council (Ecnec) approved the project having an estimated cost of Tk1.7335bn.
Of the total project cost, Germany’s KfW will provide $9m on loan, while Tk682.39m would come from the government exchequer. The rest of Tk141m will be borne by DPDC.