Ctg residents unhappy over hurried inauguration of unfinished projects

Update : 12 Oct 2013, 08:32 PM

People from different walks of life in Chittagong have expressed their dissatisfaction, as eight projects of Chittagong Development Authority (CDA) out of the total 11 inaugurated by the prime minister on Saturday, remain incomplete.

Locals and city planning specialists alleged that eight projects, including Bahaddarhat Flyover project, were inaugurated hurriedly in incomplete states only for political motives.

The locals were also disappointed as Prime Minister Sheikh Hasina was physically present only for the inauguration of the Bahaddarhat flyover, while she inaugurated the other projects in a digital way from the Jamiatul Falah Mosque grounds.

With the prime minister and government high-ups opting out from visiting the actual project sites, the CDA allegedly inaugurated the projects in incomplete conditions.

City planning specialists said it would take more time for Chittagong residents to reap the benefits from the projects, as other project-related systems needed to be upgraded before proper service could be ensured.

The Bahaddarhat flyover, officially called MA Mannan Flyover, is almost completed, but its adjoining roads and other flyover-related works were still under construction, said CDA sources.

Nazrul Islam, secretary of Bahaddarhat Traders Welfare Association, told the Dhaka Tribune that the flyover will not bring any benefit if the adjoining roads were not expanded and repaired.

This correspondent visited the inaugurated Dewanhat overpass on Saturday, to find it in a half-completed state.

The same condition was also found for the Dhaka Trunk (DT) Road (Alangkar-Dewanhat) expansion project, during a visit on Saturday.

Some areas of the roads Pahartoli, Mansurabad, Askarabad and Dewanhat overpass were still not carpeted, while some portions of the roadside were illegally occupied, the Dhaka Tribune also found.

Omar Faruk, financial director of a private developer company, said although the construction work of the overpass and DT Road were half-completed, the locals who use the Dewanhat intersection would continue to suffer as the speed for completing the rest of the work would be lessened after the premier’s visit.

Sources at the CDA also said the carpeting of Arakan Road (Bahaddarhat-Kalurghat) was completed, but other maintenance works were still incomplete.

However, Mahfuzur Rahman, CDA project director (PD) for the three projects, gave his “assurance” that the remaining tasks for the three projects would be completed within November.

“As the government’s tenure is ending, we were compelled to inaugurate the projects in incomplete state,” he said.

The Kapashgola Road (Gani Bakery-Bahaddarhat) project, which was granted by the Ecnec, was inaugurated as College Road project (Gani Bakery-Oli Kha Mosque), as only that portion was completed, said CDA Engineer AHM Misbah Uddin, the PD of the project.

Seeking anonymity, a senior CDA official also said: “As the rest of the work for Kapashgola Road is not finished, so the CDA mentioned the project’s one part as College Road and took recognition from public; but it is deceiving."

Meanwhile, locals alleged that construction tools, sand and bricks were kept on the roadsides for the Oxygen-Oli Kha Mosque and Oxygen-Kuaish road expansion projects, causing sufferings for commuters.

Ashraful Alam, a local, said commuters faced trouble every day as three-fourth of the carpeting for Oxygen-Kuaish road was unfinished.

“The roadsides are occupied by illegal occupants and construction materials, which causes tailback on the roads most of the time,” he said.

The Dhaka Tribune was unable to reach CDA Engineer Md Sahabuddin, PD for both the roads, for his comments as he did not pick up his mobile phone despite repeated attempts.

Among the incomplete projects, the Pathantuli Road expansion project was in the best condition, but still required some maintenance tasks, while construction of a new nine-storied building known as New Market “B” block was still going on, said CDA sources.

Subhash Barua, vice-president of Forum for Planned Chittagong and also a former master planner of CDA, told the Dhaka Tribune that the projects were unplanned and people failed to get traffic-related seven projects of top priority.

Commenting that road expansion or flyover construction were not permanent solution to traffic jams, he said the expanded portions of the roads were illegally occupied, while the flyover would only shift tailbacks.

Saying that private cars represented only five percent of the traffic, Subhash said the proposed and constructed flyovers and overpasses were planned for only five percent, while the 95 percent which consisted rickshaws, CNG-run auto-rickshaws, tempos, human haulers and buses were being ignored.

The common people will not benefit from these projects if concerned authorities did not improve traffic management and law enforcing measures related to traffic and roads, he added.  