Already behind the schedule by nine months, the grid interconnection project will not be able to add more than 175MW before November as work on substation and transmission line have not been completed yet.
The test transmission of electricity from India began around 10:45am on Friday at Kushtia’s Bheramara substation for the first time, adding 50MW to the national grid. By September 30, this would increase to 175MW, project officials said.
The project, which aims at purchasing 500MW electricity from India, was scheduled to be completed within December last year at a cost of Tk10.79bn.
Although the project cost has been revised upward by Tk5bn, officials now say it will not be fully ready to transmit 500MW from India before November.
However, Prime Minister Sheikh Hasina is set to inaugurate the commercial transmission of power imported from India on October 5.
Her Indian counterpart, Manmohan Singh, is expected to join the inauguration programme via video link from Delhi.
“We have started importing power from India for the first time on an experimental basis with limited scale. We hope that a total 500MW will be imported from India by November this year,” acting managing director of the Power Grid Company of Bangladesh (PGCB) Chowdhury Alamgir Hossain told the Dhaka Tribune on Friday.
Kazi Ishtiak Hasan, project director of Grid Interconnection between Bangladesh (Bheramara) and India (Bahrampur), said work on some equipment of the substation and the transmission line would end in November this year. Until then, the transmission would be limited to 175MW although the project’s installed capacity was 500MW.
On February 19, the Executive Committee of the National Economic Council (Ecnec) gave nod to the PGCB about the revised project to construct grid interconnection between Bangladesh and India for supply of electricity.
The cost of the project has been increased to Tk15.79bn from the original outlay of Tk10.79bn.
The PGCB under the Power Development Board was scheduled to implement the project by 2012.
The project includes construction of 27km transmission line and two substations and acquisition and development of 113 acres of land.
The cost of 1kW of electricity from India is expected to be Tk4 with a wheeling charge of Tk0.80. The PGCB will charge the PDB Tk0.23 per unit.
Dhaka and New Delhi signed a memorandum of understanding to import 500MW of electricity in January 2010 during the visit of Sheikh Hasina to India. Bangladesh was supposed to get 250MW of electricity from India in July this year, but the deadline was missed because of a delay in the setting up of transmission lines on the Indian side.