The construction work of the long-awaited Dhaka Elevated Expressway is unlikely to commence during the tenure of the present government as much of the groundwork of the project has not yet been done.
Bangladesh Bridge Authority (BBA) high officials failed to say anything about the construction work of the expressway.
Kabir Ahmed, BBA chief engineer and project director in-charge, said: “We cannot give you any deadline; it depends upon the government decision.”
“Every big project like Dhaka Elevated Expressway (DEE) always needs some extra time to kick off. We are working on it,” he said.
Communications Minister Obaidul Quader on different occasions said field level work for the construction would start in August this year.
The minister in June this year said the construction of the expressway would end in three phases.
In the first phase 8-km route from Shahjalal International Airport to Tejgaon would be constructed. Another 8-km from Tejgaon to Kamalapur and a 7-km route from Kamalapur to Kutubkhali near Dhaka-Chittagong highway would be completed in second and third phases respectively.
Frequent changes in design of the expressway has contributed to changes in its length times and again until the final decision to build a 23-km expressway excluding ramps was taken, according to the information of the communication minister.
The DEE will be built under a Public-Private-Partnership (PPP) project at a cost of Tk87.03bn. Of the cost, the government will provide Tk22.58bn and the rest will come from private contractor company.
According to the BBA, the route of the DEE will start from Shahjalal International Airport and run alongside the New Airport Road via Mohakhali, Tejgaon and Moghbazar to Kamalapur Railway Station before it passes through Golapbag to get connected to the Dhaka-Chittagong highway near Kutubkhali.
The DEE is a component of the 20-year Strategic Transport Plan and also one of the largest transport projects.
The expressway is aimed to reduce traffic congestion and ease movement of commuters and vehicles from different corridors of the capital city.
On January 19, 2011 the government signed a deal with the Bangkok-based Ital-Thai Development Public Company to construct the four-lane Dhaka Elevated Expressway.
The groundwork of the project started on April 3, 2011 and the construction was scheduled to kick off in July of the same year and end in 42 months. Later the it was rescheduled for March, 2012.
Awami League lawmaker and former communications minister Syed Abul Hossain in June, 2010 said the government aimed to complete the first phase of the Dhaka Elevated Expressway project within its tenure.
Moreover, as per the deal, the construction should be completed by June 2014 which in present context is not feasible.
An official of the BBA seeking anonymity said it was not possible to start the construction of the elevated expressway within the tenure of the present government.
The construction of DEE faced delay for the lengthy process of land acquisition, design change and lack of sufficient fund.
When asked about the progress in the construction work Chief Engineer Kabir Ahmed said the Bangladesh Bridge Authority Executive Engineer AHMS Aktar knows everything about it.
When contacted Aktar said: “Though the construction has not started, the project work is going on. We will inform you more about the DEE including the starting time of the construction the next week.”