The 412MW (megawatt) gas-fired Haripur Combined-Cycle Power Plant, the largest public sector power plant built under the Awami League-led grand alliance government, could not begin its commercial operations Friday, as planned.
The implementing agency of the plant, Electricity Generation Company of Bangladesh’s (EGCB) Managing Director, Mostafa Kamal told the Dhaka Tribune, the steam turbine generator was not ready to run, and due to a damaged gas booster compressor, the plant could not start commercial operations.
“Commercial production will probably start next week,” Mostofa Kamal hoped. He urged the government to ensure proper gas supply to the plant for full-fledged operation.
On August 24, Prime Minister Sheikh Hasina inaugurated the formal operation at the power plant.
Meanwhile, Bangladesh Power Development Board (BPDB) sources said the government may shut down the inefficient 96MW Haripur Power Plant under the PDB, to supply gas to the 412MW Haripur Combined- Cycle Power Plant.
In addition, an EGCB official seeking anonymity said other gas-based power plants might as well face shortages in supply due to the new plant.
After Prime Minister Sheikh Hasina had laid the foundation stone of the plant on March 20, 2011, the state-run EGCB constructed the plant with the assistance of Marubeni Corporation of Japan as the Engineering, Procurement and Construction (EPC) contractor.
The plant would require 64mmcfd gas to operate in full capacity while production cost of per unit of electricity here would be Tk1.7154.
The government has implemented the power project at a cost of $376m with financial support from Japan International Cooperation Agency (Jica).
Sources at the PDB said, electricity generation in the country Friday was about 6200MW against a projected demand for 7000MW.