Fund shortage delays four-lane work

Update : 10 Sep 2013, 08:39 PM

The government has so far taken no action against the Chinese company mainly responsible for the delay in completion of construction work of the four-lane Dhaka-Chittagong highway.

Communication Secretary MAN Siddique has recently told this correspondent that fund shortage of the Chinese company is the main reason behind the delay.

The other factors for the delay, he said, are frequent shutdowns, shifting of graveyards, schools, and places of worships.

“We had to negotiate with local people and leaders to shift those structures. It took lots of time, but we have already done it,” he added.

The government is now planning to pressurise the foreign contractor to finish the construction work within the stipulated time according to the revised development project proposal.

If the government cancels the contract it may cause more delay, he said, as it involves fresh tender to appoint new contractor.

“It will also push up the expenses of the project because a new contractor will offer a new price which has already been hiked several times,” Siddique observed.

Explaining the delay he said the government was to pay 80% expenditures of the completed work while the contractors were to pay the rest 20% from their own resources.

The Chinese company failed to collect the money from their country resulting in the delay in construction work.

The ministry of communication has already met Chinese deputy minister who visited Bangladesh recently and Chinese Ambassador in Dhaka to ensure adequate supply of money from China as maximum construction work of the projects was awarded to Chinese contractor.

Most of the Chinese construction firms are owned by their government. They have assured of providing the fund during the next summer.

“If the fund is provided on time the work of the project may be completed within the stipulated time,” he added.

But, the Chinese Embassy officials concerned declined to comment on the matter. While communicated its Attaché on Media Affairs Ye Wei both over phone and in e-mail message said they were unaware of the problem.

According to the revised development project proposal, the Dhaka-Chittagong four-lane highway project was to be completed by December 2014. Originally, the project was scheduled to be completed by the end of the current year.

Communication ministry officials related to the project in return for anonymity said the progress in the work of Dhaka-Chittagong four-lane highway slowed down one and a half years before the deadline although its budget constraint was solved.

The progress of the Tk32bn project was “unsatisfactory” as only 38% work was completed until June against the release of more than one-third of the budgetary allocation. Bitumen covering of only 17km out of the highway’s 193km length was completed by June.

The finance ministry released Tk11.21bn until June at the end of the fiscal year (FY) 2012-13 but the construction firms completed the work equivalent to about Tk7.85bn.

About the progress Siddique said: “It’s not that we are satisfied with the progress of the projects. But it’s true that shutdown of the opposition is a major problem for completion of the work.”

The foreign contractors are not interested in working for security reason during the shutdown. But they agreed to receive materials during shutdowns which is a positive gesture.

“We have already completed construction of most of the bridges and culverts. The early onset of monsoon slowed down the project work over the last few months.”

He hoped that the work could be completed by the next summer.

According to the ministry officials, out of the total 244 culverts and 23 bridges construction of 228 culverts and 13 bridges were finished during the last fiscal year.

The Roads and Highways Department under the communications ministry has awarded 192.3km Dhaka Chittagong four-lane highway work to three construction firms Sino Hydro Corporation Ltd of China, Reza Construction Ltd and Taher Brothers-ACL joint venture of Bangladesh in 2010.

As per the agreement the Chinese firm has to complete 70% of the work in seven packages while the two Bangladeshi firms the rest in three packages.

About the allegation of allocating a poor budget for the project, the secretary said it was increased in the last fiscal year. In the current FY Tk5.50bn has been earmarked.

“The progress on the roads stretching from Mirershorai Bazar to Panchashila Bazar, and from Batisha via Mohipal to Dhumghat and from Panchashila Bazar to Comilla Bypass is not satisfactory,” said the ministry officials.

According to the ministry, 90% earthworks have been completed and utility lines shifted. The construction firms would be able to finish the rest of the four-lane highway’s work during the next two dry seasons.  