The construction work on an elevated expressway connecting Shantinagar in the capital to the Dhaka-Mawa road may not be commenced in the tenure of the present government as much of preparation work for the project remains incomplete.
Officials of Rajdhani Unnayan Kartipaksha (Rajuk), the company in charge of the project, said they needed at least six months to start the construction work of the expressway as they had only started paper work for the project.
In January of this year, the cabinet committee on economic affairs gave the go ahead to a proposal for construction of a 13.32km expressway from Shantinagar to Dhaka-Mawa road in Rajuk’s Jhilmil Residential New Town Project.
The project will be implemented under the Public-Private Partnership (PPP) initiative, aiming to ease traffic congestion in the capital.
The flyover project was undertaken as per the directive of Prime Minister Sheikh Hasina in order to establish direct and smooth vehicular movement from Padma Bridge to the Jhilmil Residential Model Town.
The Ministry of Housing and Public Works (MoHP) and Rajuk will implement the Tk26.7bn project. It is expected to be completed in 2016.
Rajuk officials said they had made a project proposal for the flyover and it would be submitted to the MoHP, Planning Commission and Executive Committee of National Economic Council for final approval.
After final approval from the government agencies, the housing ministry and Rajuk will appoint private companies as consultants for funding the flyover, the officials added.
Rajuk completed a pre-feasibility study on the expressway last week.
A Rajuk team, led by engineer and project director of the flyover Md Abdul Baki Miah, visited the project route.
It was determined that Shantinagar will be the starting point of the expressway to coordinate it with the Moghbazar-Malibagh flyover.
According to the project proposal, the expressway will pass through existing roads at Bijoynagar, Purana Paltan, Phulbaria intersection in Gulistan, Naya Bazar intersection, Babu Bazar and Buriganga second bridge, ending at the Jheelmil housing project beside Dhaka-Mawa road.
The flyover will also be connected with Victoria Park in the Sadarghat area.
Project Director Abdul Baki told the Dhaka Tribune: “We have just started the project study, it is not the right time to say anything about the flyover.”
He said although they had visited the proposed project route recently, it was not the final route of the flyover.
Baki also said: “If the government gives approval to the project, a consultancy firm will be appointed, which is a lengthy process and it will take at least six month to start the construction.”