The Mirpur Grameen Bank-Agargaon link road is going to miss its completion deadline as the construc-tion work is being conducted at a snail’s pace, due to the indifference of Dhaka North City Corporation (DNCC).
Although the construction work of the project had started in 2010,the DNCC suspended work due to difficulties in acquiring land for the project. It started the construction work again in 2012.
Now, the construction of the road is slated to be completed by the end of 2014.
Md Delwar, a resident in the area adjoining the proposed road, told the Dhaka Tribune: “Although the city corporation had started the project a year back, it had spent all that time in acquiring land for the project.”
“They come occasionally to visit the site, but do not take any steps to start construction of the road,” he added.
Md Kamal Hossain Mollick, another resident of the area, said: “The city corporation acquired land only from individuals, but could not acquire land from the post office and the local school for the project.”
Meanwhile, officials of DNCC said the project is delayed due to difficulties over land acquisition.
Project Director Abdur Razzque said: “The project remained suspended from 2010 to 2012 due to diffi-culties over land acquisition.”
“Now the construction is delayed since the installation of the sewerage and drainage line has to be completed first,” he said, adding, “Once the laying of these lines is over, we will start construction of the road”.
The proposed link road, to be built at a cost of Tk2.4b will be 3.5km long and 60 feet wide, with four lanes and a footpath and will stretch from near the Grameen Bank headquarters at Mirpur-2 to Agar-gaon.
The Dhaka Water Supply and Sewerage Authority (DWasa) is also working with DNCC to implement the project.
On a recent visit to the project site, this correspondent found that work remained suspended.
Following even light showers, the people living near the project site, have to suffer as the mud around the site makes it difficult for them to walk through.
The authorities have piled the sewerage and drainage pipes on both sides of road, obstructing peo-ple’s movements. It has been more than a year since these pipes were brought to the project site but they are yet to be used.
However, DNCC Chief Engineer Mohammad Abul Khayer denied the allegation that the construction work had been suspended and claimed that work had just been stopped during the eid holidays and will recommence after the holidays.
“We hope the construction will be finished in this fiscal year,” he added.