Dynamite explosions and collection of data through GPS system have kicked off at the Sunetra structure in Netrakona as part of a three-dimensional (3D) seismic survey to assess the gas reserves there.

“We started dynamite explosions on Friday and are recording the sounds through geophones to collect data through GPS. The data will then be processed and examined,” MA Baki, managing director of state-run Bangladesh Petroleum Exploration and Production Company Limited (Bapex), told the Dhaka Tribune yesterday.

He said: “Once the seismic survey is complete, we will be able to know the actual quantity of gas reserve and determine the locations for further exploration.”

The 260sqkm structure has been named Sunetra, as one part of it falls under Sunamganj district and the rest in Netrakona. Recently, a new exploration well was dug in Sunetra, where no gas was found. Bapex has decided to conduct a 3D-seismic survey there.

In addition to building structures for conducting the survey, the Bapex MD said dynamites were also planted at designated short points for recording the sound of explosions.

Baki said the survey would be completed in three different phases: data collection (survey, seismic drilling and sound recording), data processing and analysis.

The project director of 3D-seismic survey Meherul Hasan told the Dhaka Tribune that the work was supposed to start in February and complete by June, but it was delayed as explosives did not arrive in time.

The work will not be finished in time due to negligence, officials said, adding that six more months would be required to complete the task and the rainy season is another obstacle.

Bapex MD Baki told the Dhaka Tribune: “We will start phase-by-phase 3D-seismic survey in four fields covering a total area of 1,550sqkm.”

The plans include 260sqkm in Sunetra, 440sqkm in Sundalpur, 600sqkm in Shahbajpur and 250sqkm in Shemutang gas fields.

Work at the three other fields would begin in November, he added.

Meanwhile, Bapex has already completed 3D-seismic survey at six gas fields: Bakhrabad, Salda, Rashidpur, Kailshtila, Titas and Haripur.

It later revealed the findings at these fields after analysing the survey data. According to the report, one trillion cubic feet (TCF) of gas was found in Rashidpur. This was the first-ever 3D-seismic survey conducted by the state-run exploration agency.

Meanwhile, Kailashtila and Haripur fields contain proven reserves of 137m barrels of crude oil, of which 55m can be lifted commercially.

Bapex’s seismic survey team also disclosed that the country’s largest state-run onshore gas-field, Titas, now has a recoverable reserve of 2.91TCF remaining after producing from the 6.36TCF estimated previously.

Findings at Bakhrabad and Salda, each of which covers an area of 210sqkm, will be disclosed later next month, said officials.