Corruption in land acquisition and Environmental Impact Assessment (EIA) reporting afflicts two major power projects, Transparency International Bangladesh (TIB) claimed.
The watchdog unveiled a report titled “Rampal and Matarbari Power Projects: Challenges of Good Governance on Land Acquisition and EIA” at a press conference in the MIDAS Centre in the capital yesterday.
It was presented by TIB researchers Mohammad Hossain and Md Rabiul Islam.
TIB Executive Director M Iftekharuzzaman conducted the talk while TIB Board of Trustees Chairperson Sultana Kamal chaired it.
A 1,320MW coal-based power plant is slated to be built at Rampal. Another 1,200MW plant at Matarbari, financed by the Japan International Cooperation Agency (Jica), is on the cards as well.
Iftekharuzzaman alleged that Jica misappropriated climate change funds by giving the money to Bangladesh in loans instead of as grants.
Despite mounting protests, Japan continues to finance the building of coal-fired power plants with money earmarked for fighting climate change, with two new projects under way in India and Bangladesh.
Japanese officials say they are counting some $630 million in loans for coal plants in Kudgi, India, and Matarbari, Bangladesh, as climate financing.
Tokyo says the projects are climate-friendly because the plants use technology that burns coal more efficiently.
The TIB report also said Tk23cr had been misappropriated by authorities at Matarbari. Iftekharuzzaman said the two plants require independent monitoring.
Bangladesh and India are jointly implementing the Rampal power plant project at a location close to the Sundarbans, the world’s largest mangrove forest and a Unesco world heritage site.
Environmentalists vigorously oppose it.