Only 70pc work done in Comilla

Update : 22 Mar 2015, 07:38 PM

The Dhaka-Chittagong four-lane highway is facing further delays due to slow implementation in the stretch that goes through Comilla.

Although that stretch was scheduled to be completed within three years, only 70% work has been done in four years.

According to the sources, out of the 192.3 kilometre of the project, 99 kilometre lies in Comilla district stretching from Daudkandi toll plaza to Feni’s Mohammad Ali area.

So far only 55km of 99km has been upgraded and paved. All the bridges and culverts on this portion have also been completed.

The four-lane upgrade project began in 2010 and was expected to be completed by 2013. Three construction companies are in charge of the project implementation.

China-based Sinohydro Corporation is in charge of the major portion of the project while the rest are done by Reza Construction and Ms Taher Brothers.

A recent visit to the site found that construction materials on both sides of the road in Comilla’s Daudkandi and Chandina were creating traffic congestion. Moreover, the crooked road in Chouddogram area was also blamed for slow traffic movement.

Driver of Tisha bus service of Comilla, Mafiz Uddin said it took him about two hours extra to go to Dhaka because of the traffic congestion.

Another bus driver Kamal Hossain said the 42-km area of Chouddogram was not paved properly causing bumps and uneven surface hindering smooth movement.

Manager of the four-lane project Masum Sarwar said all major works like land development, bridge construction, culverts, embankment and other areas had already been done.

“We are very sincere in finishing the rest of the work very soon since this is a high priority project. We had a meeting on the progress on March 12 and hope to complete it within this year,” he added. 