A government monitoring committee has decided to closely observe the implementation of the seven fast-track priority projects to ensure transparency in tender processes under 11 modalities.
Following their third meeting yesterday at the Prime Minister’s Office (PMO), one of member of the committee told the Dhaka Tribune that they had approved the monitoring modalities in a meeting presided over by Prime Minister Sheikh Hasina.
The official also said the committee also expressed satisfaction over the progress of the large-scale projects including the Padma bridge and metro rail; on an average, more than 40% progress have been made in all the seven fast-track projects.
The other projects are: deep-sea port; 1,320 megawatt Rampal Power Plant; Matabari 1,200MW power plant; 1,000 MW Rooppur Nuclear Power Plant; and LNG Terminal.
It was discussed in the meeting that allocation and acquisition of necessary land for building the MRT Line 6 of the metro rail have been completed.
Rajuk gave 40 acres of land to Communication Ministry a couple of months ago.
In June last year, the work for a geo-technical survey was inaugurated; the detailed design will be completed by July.
It was also discussed in the meeting that around 30% work for the Jajira approach road of the Padma Bridge has been finished and 22% of the Mawa approach road.
The work for the service area has progressed 15%, the main bridge construction 1%, land acquisition 99% and rehabilitation work 65%.
The ADB will also regularly recommend the first-track task force based on the monitoring outcomes. One of the modalities follows an ADB recommendation that monitoring will be easier if the ministries and divisions concerned prepare budgets for projects.