Ashuganj power plant fixes 5 units, starts production

Update : 01 Nov 2014, 03:49 PM

Ashuganj power plant has fixed five units out of nine after a six-hour long effort which were shut operations during unusual power outage over the entire country following the national grid collapse.

The five units came to regular electricity production around 6pm on Saturday.

Engineer Sajjadur Rahman, director of the power plant (Technical) endorsed the information to the Dhaka Tribune.

He said: “After a six-hour long effort by our engineers could manage to fix four quick rental and one gas turbine plants out of nine plants and the units started regular production.”

Earlier, the five plants were fixed also started production around 4:30pm but the production was shut within few minutes, he said.   