ADP execution rate at 5-year low

Update : 31 Oct 2014, 07:40 PM

The execution rate of the annual development programme (ADP) hit its five-year low in July-September this fiscal year despite the government’s massive development plans.

The latest official data of the Implementation Monitoring and Evaluation Division (IMED) of the Planning Ministry reveals that the rate dipped 9% in the first quarter ending in September.

Officials at the division said ADP implementation was 11% in the first quarter of the last fiscal year. The rates were 13% and 11% in the corresponding periods in the previous two fiscal years.

An official of the Planning Commission said Minister AHM Mustafa Kamal had taken several initiatives for 100% execution of the ADP in the first month of this fiscal year but it had failed to show any signification improvement.

IMED data also reveals that four of 10 major ministries and divisions are yet to start their ADP projects for the first quarter of FY2014-15.

The government agencies concerned have so far managed to spend Tk7,025 crore, excluding the self-financed projects of the public corporations, from a total ADP outlay of Tk80,315 crore for FY2014-15.

Former caretaker government adviser AB Mirza Azizul Islam said the mega projects of the ADP were responsible for the deceleration of the ADP implementation.

Among the major ministries and divisions, the Local Government Division spent the highest 16% of its allocation, the Education Ministry 13% and the Primary and Mass Education Ministry 11%.

The Power Division, which got the second highest allocation in the ADP, has been able to spend only 8% of its fund in the first quarter, while the Bridges Division spent only 9% of its allocation, which was the third highest.

The 10 ministries and divisions – large in terms of allocation, which is 72% of the total allocation – could spend only 10% in the first quarter of this fiscal year. 