At a time of acute power crisis four years ago, the Speedy Supply of Power and Energy Act was promulgated as a temporary solution for quick disposal of energy and power-related decisions, despite the fact that it was heavily draining for the state coffer.
However, in what appears to be an attempt to give the temporary arrangement permanence, the cabinet has once again extended the tenure of the two-year act – this time until October 2018. The tenure was extended once before in 2012 by two years.
A regular meeting of the cabinet yesterday approved a draft of amendment for the Speedy Supply of Power and Energy (Special Provision) Act 2010 in line with a proposal from the Power, Energy and mineral resources Ministry. Prime Minister Sheikh Hasina, who also in-charge of the power ministry, chaired the meeting at the Secretariat.
The act was promulgated what officials said was to simplify the approval of power projects and bringing generated electricity quickly to the national grid.
Many have opposed the act because it gave the government a certain degree of “indemnity” in implementing project decisions, especially the highly expensive fuel-oil-powered quick rental power plants.
The act empowers the government to do “whatever necessary” to save time and red tape tangles, to the extent of going against the Public Procurement Act by undertaking projects without floating tenders.
It also says the legality of any of the decisions made, steps taken and orders given under the act cannot be challenged in future before any court of justice. Moreover, even after the expiry of the act, any work or step taken under it should go on in a way that the law has not expired.
Buet Professor Ijaz Hossain told the Dhaka Tribune: “This act is harmful for the country. It was enacted with an aim to bypass the existing public procurement act.”
He also said: “This act has had a number of negative impacts on the power sector. We are falling behind in terms of technology because the power plants implemented under the act are by and large of low energy efficiency. Because the act was enacted on a temporary basis, the entrepreneurs installed less efficient and old machinery at cheap price in the quick rental power plants as they thought they would not be needing them after a couple of years. They are now using the same old machinery to produce electricity now. As a result, they are needing more oil and production cost is skyrocketing.
“If we had a prior plan to run these power plants for seven to eight years, we would have been able to install better machinery that could have generated combined-cycle power instead of simple-cycle power. In that case, we would have been able to generate more power with these power plants,” explained Ijaz, who teaches chemical engineering at the Bangladesh University of Engineering and Technology (Buet).
“The plans for building the large power plants did not make the desired progress. As a result, the government was compelled to invest in the expensive short term solution. But as there is no other alternative, the government is now turning the short term solution into a long term one,” he said.
Under the special act, the government has so far signed agreements on setting up the country’s first floating storage and re-gasification unit, better known as LNG terminal. A total of 10 wells at six gas fields are currently being drilled and more than 25 quick rental and two independent power plants are operative under the act.
Additionally, the government has already made decisions to build a second unit at the Eastern Refinery Limited in Chittagong and build a number of medium-sized independent power plants under the act.
After the meeting, Cabinet Secretary M Musharraf Hossain Bhuiyan said approval had been given to the draft for amending the act on condition of vetting by the Law Ministry.
It would be placed in the next session of parliament due to start on September 1, he said.
“The extension was needed for achieving the power generation target as existing rules were creating obstacles for quick disposal of decisions related to the awarding of projects,” Musharraf said.
State Minister for Power Nasrul Hamid told the Dhaka Tribune yesterday: “The tenure of the act has been extended for the greater interest of the country. It was needed in order to ensure the continuation of the ongoing projects and the completion of the unfinished ones under the act.”
The heavy burden
According to sources, the Power Development Board (PDB) is going to spend a total of Tk582.24 crore in the form of subsidy for paying the bills of quick rental power plants for the month of June. This amount comprises 73% of the Tk790.13 crore that the Finance Ministry has given as credit to the PDB for the month of June.
In May this year, the PDB spent 80% of the credit that it had got from the Finance Ministry, for paying quick rental bills.
The Dhaka Tribune has accessed a letter that the Finance Division had sent to Power Division Secretary Monowar Islam yesterday, disbursing the loan to the PDB at 3% interest rate.
In 2009, when the government depended much less on fuel oil-based quick rental power, the amount of subsidy in the sector was Tk994 crore.
However, in 2013, when the price of fuel oil and the government's dependence on quick rental power increased manifold, the amount of subside rose to more than Tk5,170 crore.
According to official figures from October 2013, 97% of the power sector subsidy went into paying the bills of the privately-owned quick rental power plants.
According to PDB, the average cost of producing power using natural gas is around Tk2 per unit and per unit of coal-fired power costs around Tk6 per unit.
On the other hand, the cost of producing power using fuel-oil is around Tk14-20 per unit, which is around 10 times that of gas-based power.