Road digging causes sufferings for commuters

Update : 21 Aug 2014, 10:01 PM

Residents of Rajshahi City Corporation have been suffering immense woes as around 6,000 ditches, dug by the authorities along around 410km roads in the city to facilitate new gas connections, are not being repaired properly.

After visiting different parts of the city, this correspondent has found irregularities in the repair works of the roads. Small ditches have turned into large ones and most of the roads are being decayed due to lack of proper repair works since last four years.

The authorities concerned had started providing new gas connections to the city dwellers since last June and around 6,000 consumers were provided with new connections after digging same number of ditches along different roads.

Although the consumers are charged the road repairing costs, ranging from Tk97 to Tk3,190, the ditches on the roads are not being repaired properly.

Paschimanchal Gas Company Limited (PGCL) sources said city corporation authority’s permission to dig the roads and road repairing costs from the consumers had to be taken before providing the connections.

The PGCL has set around 271km gas connection pipe lines before January 30, 2012 spending around Tk97 crore. Though the ditches dug for these connections are supposed to repaired jointly by the gas distribution company and the city corporation authorities, most of the roads are yet to be repaired completely.

It is alleged that lion share of the compensation money provided by the consumers is being looted by the authorities concerned before the money is deposited in the city corporation fund.

Rokeya Begum, one of the consumers in Baliyapukur area, told the Dhaka Tribune that she had deposited Tk2,583.90 through city corporation slips. After contacting the city corporation branch of the Agrani Bank later, she, however, found that only Tk84 was deposited in this connection.

Contacted, acting manager Tofael Ahmed of Rajshahi PGCL denied the allegations, saying the PGCL had nothing to do with the repair works. The compensation money was taken by the city corporation authorities and they were solely responsible for the repair works of the roads, he claimed.

Meanwhile, Rajshahi City Corporation’s Chief Engineer Ashraful Haque said: “The roads were not being repaired because of the rainy season.”

The compensation money provided by the consumers was being deposited in the city corporation fund properly and the roads would be repaired soon after the rainy season, Ashraful told the Dhaka Tribune. 