A one kilometre road on Dhaka-Khulna highway near Kharikhali under the district Sadar upazila was damaged within a week after its repair.
The Roads and Highways Department carried out the repair spending Tk14 lakh.
Sources related to the department in Jhenaidah said a large number of small and large potholes, plus cracks emerged on the road posing risks for vehicles to move, not to mention the sufferings of the pedestrians.
The motor vehicles were plying on the road with the risk of lives and properties.
The authority concerned invited tender for road carpeting, using stone chips and bitumen.
But, just a week after repair to the one-kilometre road with a 12 milimetre (half an inch) coating of stone chips and bitumen, large potholes developed on it.
Locals said the contractor used sub-standard materials and made the road surface five to six milimetres thick instead of the prescribed 12 milimetres.
The road started getting damaged within a week, just five days after its repair.
Stone chips and other materials began decaying from the surface and cracks developing there.
Contacted, the road contractor, Motiar Rahman, alias Runi, said he did his best, but he refused to comment on why the road turned unfit for traffic movement so quickly.
The schoolboys under Jhenaidah Sadar upazila said the roads were now posing risks for them to commute between their houses and schools.
A source said since Motiar was the lowest bidder for the contract, Tk13.89 lakh only, the authority offered him the construction work.