All the development projects under Rajdhani Unnayan Kartipakkha (Rajuk), such as new satellite towns, constructions of other housing projects, and city development schemes are behind their completion deadlines as progress has been very slow.
The reasons behind the slow progress are negligence and irregularities, repeatedly changing high officials in tenure of different government, wrong selection of bidders, sheer dilly-dallying in land-acquiring move and delay in starting the groundwork.
Sources at the Rajuk said every time after changing the government, they had to accept changes in every project as the government appoints new officials and project directors on political considerations.
Moreover, contractors of different projects, who got the job by bidding lower than the estimated costs, sometimes deliberately delay the work to obtain more money by using political influence.
Currently, Rajuk runs 19 big projects in and around the city where it has to build apartments, roads, bridges, flyover, and has to improve the condition of lakes.
Development of Purbachal New Town Project, which was planned to be developed by possessing land at Rupgonj in Narayanganj and Kaliganj in Gazipur, started its project 20 years ago.
But the project has failed several deadlines, and it’s yet to be completed.
Rajuk officials said the revised timeline of the 24,697-plot project was July 1995 to June 2012, but the deadline had to be extended to December 2015 as construction works were not completed.
The government planned the satellite city Purbachal New Town Project in 1992 and land acquisition started in 1993. Moreover, the 300 feet wide Purbachal Link Road also missed its completion deadline. Besides, there have no initiatives about the 20,000-flat project in Purbachal.
Development of Uttara Residential Model Town’s third-phase started in 1999-2000, and the site development and infrastructural construction began in 2004, but the construction is still undone.
Besides, Rajuk has faced early complications as the Covenanted Construction Company delayed to start the construction work of the Uttara apartment project
Rajuk’s other project Jhilmil Residential Area, started in 1997, is also yet to be completed.
The project located at Keranigonj and comprises of 381.11 acres of land where the authorities started to handover the pots to owners recently.
But Rajuk did not take any step to start construction of 9,500-flat project in the new satellite city.
Rajuk plans to handover flats to the affected land owners of the adjoining areas of the Hatirjheel-Begunbari Project by 2014. Allocation of flats was supposed to be started by December 2013, but it has not started yet.
Integrated development of Hatirjheel-Begun Bari canal, Gulshan-Banani-Baridhara lake development and the beautification of the projects are also delayed, while Utara lake improvement has not started yet.
However, Rajuk Chairman Nurul Huda denied the allegation of appointing contractors on political considerations.
He added that they need additional time to solve the problems, but admited that they are in manpower crisis.
But he claimed that land developments in all new towns have already completed, construction of all roads, bridges are near to be completed, and they have already started to hand over the plots.