Infrastructure and power lines are in such a state of disrepair that it mars the present government’s success in achieving increased power generation, as frequent electricity outages continue unabated across the country.

According to the Power Division electricity generation has increased by 104.25% and distribution lines were extended by 9% between 2009 and 2013 since 2009. Though electricity generation more than doubled, consumers have not reaped benefits with no visible improvements in terms of distribution and supply in these four years.

“Enough steps have not been taken to improve the distribution system to cope with the increase in power generation,” said Syed Abdul Mayeed, former chairman of the Power Development Board (PDB).

He said that in fact, transformers are overloaded and damaged as they are unable to handle excess electricity generated; leaving people across the country without electricity.

The former chairman said the entire distribution system must be upgraded; more substations need to be built, old transformers replaced with new ones, but the government isn’t paying much attention to these matters.

There are five distribution companies under the Power Division, with 690, 257 transformers in total. During a coordination meeting in August, a document submitted said 135, 287of the transformers are overloaded.

The companies - Dhaka Power Distribution Company Ltd, Dhaka Electric Supply Company Ltd, Rural Electrification Board, West Zone Power Distribution Company Ltd and Power Development Board - supply through 2,85,101km of lines. Though 24,722km of new power lines for improved distributions were installed, little was done to replace the existing ones, which are in disrepair.

Seeking anonymity, an official of the Power Division said about 20% of the power supply lines are dilapidated and exposed to the elements leading to increased risks of accidents, which could result in the network’s collapse at any moment.

In 2009, when the Awami League took office, power generation capacity was at 4,942megwatts (mw), which rose to 8,949mw in July this year, said Mohammad Hossain, director general of Power Cell, and added that: “Countrywide electricity generation was 3,268MW at the beginning of 2009, which reached 6,675MW in July this year.”

Across the country, electricity coverage reaches 95.6 million people, 60% of the population, through conventional and renewable energy sources.

Desco officials said several hundred kilometres of their 3,500km supply lines are in at risk. New substations were set up but not in sufficient numbers because of scarcity of land in the capital. 

DPDC and Desco supply Dhaka, including Tongi and Narayanganj, REB covers rural areas through 70 Palli Bidyut Shomitis (PBS) and WZPDCL supplies electricity to 21 districts including Barisal and Khulna in the south-west. PDB supplies electricity to both rural and urban areas except Dhaka, Barisal and Khulna metropolitan areas.

An official said the DPDC failed to provide new connections where there is increased demand because they do not have enough substations, though six new substations have improved the situation.

An REB official said 63 of the 70 PBS are running at a loss. New power connections were not given due to overloaded transformers, but there are fund constraints.

Most of WZPDCL’s 9,000km supply lines are in a sorry state, while 10% of PDB’s 40,000 km distribution lines are also in a bad shape.

Power Secretary Manowar Islam told the Dhaka Tribune: “We have taken initiatives to build parallel lines to cope with the soaring demand for electricity, but it might take some time to repair the lines.” He added that: “Decisions have been taken to replace the overloaded transformers in phases.”  l