Expenditure on the Padma Bridge project has been sluggish, with 34.86% spent in the last three years, and the implementation of the main bridge has been minimal at just 13.5% as of August 15, according to official estimates.
But Padma Bridge Project Director Shafiqul Islam said the amount spent between FY2013 and FY2015 was not abnormal and matched up well with the amount of work done on the project.
He said he hoped the bridge would be ready for use by the middle of 2018.
A quarrel between the government and the World Bank over allegations of corruption, later proved wrong, delayed the project by three years between FY2009 and FY2012.
According to official data, accumulated spending on the Padma Bridge hit Tk8,366.65 crore as of the middle of August this year.
In FY2015-16, the government allocated Tk7,400 crore for the project while the Bridges Division disbursed Tk1,796.02 crore as of August 15.
Total project costs increased to 24,000 crore from Tk20,507.20 crore, due to delays in implementing the project.
According to the Fast Track Project Monitoring Committee at the Prime Minister’s Office, about 13.5% of the main construction work of the Padma Bridge had been completed.
The Fast Track Committee meeting, presided over by Principle Secretary Abul Kalam Azad, was held on September 13 at the Prime Minister’s Office.
According to the meeting, work on the Mawa approach road, Jajira approach road, service area 2 and river training had implementation rates of 48.5%, 50%, 46% and 8.5%, respectively.
According to the minutes from another meeting – a Bridges Division review of the project – the mobilisation work of the main bridge is currently being carried out. The Bangladesh Bridge Authority (BBA) procured has three Test Pile Drives, four Pile Testers and 18 Anchor Drives.
Some 12,400 tonnes of steel plate have been delivered to the project site, another 9,000 tonnes of it is scheduled to arrive shortly from Chittagong port and a further 7,000 tonnes is on its way from China.
River training
As of mid-August, the implementation rate of river training was at 8.5% in the Padma Bridge project.
According to a recent meeting of the Bridges Division, interim work at Magura point was completed during the rainy season to overcome setbacks due to flooding. Dredging is being continued at Jajira point.
Rehabilitation programme
The Bridges Division received an additional Tk537.18 crore to run its rehabilitation programme.
A total of 1,331 plots have already been distributed to families affected by the construction mega-project. Some 2,592 plots will be distributed under the Padma Bridge rehabilitation programme.
Another 362 plots have been distributed among landless peasants.
The government has acquired 1,230.90 out of a proposed 1,599.85 hectares of land in Munshiganj, Madaripur and Shariatpur. Land rights have been established over 1,115.44 hectares of the project site.
Environmental programme
As part of the project’s environmental mitigation effort, some 67,550 trees have been planted as of August and a contract will be signed between the Padma Bridge construction authorities and the zoology department at Dhaka University to build a museum.
Bridges Division Secretary Khandokar Awarul Islam said the construction of the Padma Bridge will be completed within the time-frame set by the government.
He said an earlier problem with the rehabilitation programme had been solved. “Construction of the main bridge will start full swing next summer,” he said.
The 6.15km long two-level Padma Bridge will be constructed of concrete and steel.
China Major Bridge Engineering Construction Company was appointed to construct the main bridge. South Korea’s Korean Expressway and the Bangladesh Army are supervising the work.