In good news for the country’s industrial sector, the government has lifted long-standing restrictions on providing power connections to industries as a result of the country producing a robust supply of electricity at the moment, after years of concerted government effort in that direction.
The process for industries to get new connections will also become easy; any industry consumer whose requirement is below 10MW would automatically get clearance if they ask for a power connection to the relevant distribution companies, according to a Power Division circular dated August 23, 2015.
If the requirement is more than 10MW, the Power Division’s clearance would have to be sought, the circular added.
Abdul Matlub Ahmed, president of the Federation of Bangladesh Chamber of Commerce and Industries, told the Dhaka Tribune: “The decision will help expedite the country’s industrial growth.”
Earlier, the power distributing companies were allowed to connect electricity up to 5MW to the industries including hotels, restaurants, and shopping malls.
In November 2010, the government imposed restrictions against new connections to industries because of an acute scarcity of power generation, as a result of years of neglect and mismanagement in the sector during the previous government.
In addition, the government has directed the electricity distribution companies to take necessary steps for ensuring power supply to the industrial units at the proposed special economic zones across the country.
A total of around 11,000 industrial units have so far applied to get additional 1,200MW of electricity from distribution companies.
The country’s electricity generation capacity is currently 11,532MW with average daily generation standing at 8,000MW. The demand for electricity is rising 10% annually.
The Awami League-led coalition government has achieved a number of successes in the power sector during the past six years. Power generation capacity has more than doubled from 4,942MW in 2009 to 11,532MW, with around 70% of the population now having access to electricity.
The government aims to generate an additional 9,600MW electricity by 2018 under short, medium, and long-term plans.