With the scheduled January 2017 completion deadline drawing nearer, there has been no significant progress in the Single Point Mooring (SPM) project although five years have passed since it had been initiated.
State-owned Bangladesh Petroleum Corporation (BPC) initiated the SPM project for handling crude oil from Kutubdia Island to Patenga in Chittagong in a bid to tackle oil pilferage and reduce time for fuel oil supply across the country.
“The Ministry of Planning has asked us for a fresh development project proposal (DPP) which pushed the project into limbo. Now we are working on a new DPP,” BPC Chairman AM Badruddoja told the Dhaka Tribune yesterday.
SPM is an infrastructure, to be built in the Bay of Bengal, from where petroleum products will be carried through pipelines from mother vessels – to be moored from offshore to oil storage tanks onshore.
“It is true that we have delayed [the project], but now we want to build the SPM quickly. Establishing the SPM is necessary for sealing the country’s energy security,” Secretary to the Energy Division, Md Abu Bakar Siddique, told the Dhaka Tribune yesterday.
After delay of over five years, the government has now set a target to implement the project by 2018.
The BPC has already received an unsolicited technical offer from a Chinese petroleum firm named China Petroleum Pipeline Bureau (CPPB) and memorandum of understanding (MoU) was signed on September 29, 2014, for building the SPM in the Bay of Bengal to carry petroleum products onshore.
The state-owned company will set up a 107km pipeline under the SPM project with investment from the Chinese EXIM Bank.
On May 20, 2011, BPC appointed ILF Engineering Consultancy, a German firm, to study the details for installing the SPM at a cost of €7.184m.
ILF meanwhile has recently carried out a fresh study and suggested changes in the project’s volume which will push up cost.
In its latest study, the German firm said BPC should build two more separate 18 and 10 inch-diameter product pipelines at the outer anchorage in the Bay to to the Moheshkhali Island to carry both crude and refined petroleum products onshore.
If these lines are built, the project implementation cost will go up to around to $446.14m, which is almost three times higher than the initial estimation.
The ILF’s previous study was on laying a single pipeline and installing the SPM near Kutubdia from where oil would be pumped through the pipeline to the shore.
On April 16 this year, the Project Processing Committee (PPC) on the SPM held a meeting on the revised DPP and asked the Implementation, Monitoring and Evaluation Division (IMED) under the Ministry of Planning to rationalise cost.
The IMED had earlier opposed ILF’s new plan of cost hike.
The government had initially estimated that the construction cost would at around $136m on the basis of a feasibility study conducted by a Pakistani firm in 2010, a BPC official said.
Jeddah-based Islamic Development Bank (IDB) had subsequently agreed to provide $129m to help install the SPM near Kutubdia Island in the Bay of Bengal.
But the estimated cost grew later when German firm ILF Consulting Engineering carried out a detailed study on the proposed SPM and re-estimated the project cost at $327m, said the official.
The IDB also later agreed to increase its funding by 70.54% to $220m.
As the government failed to arrange additional fund for the SPM project, the IDB left and the Chinese firm came up instead to build the SPM.
Installation of the SPM to carry petroleum from vessels moored at an outer anchorage to depots onshore can save both time and money.
It will help unload crude and refined petroleum products from ocean-going vessels in the deep sea without berthing at the port.
The SPM will have the capacity to unload imported petroleum fuels in two days, which usually needs 11 days with the existing facilities.
The BPC would also be able to save around Tk5bn per year by reducing pilferage from transportation of oil.