The government has decided to reduce the length of Dhaka-Ashulia Elevated Expressway to 22km, saying the original design is no longer necessary.
The expressway’s original plan depicted it to be 42km long, connecting Dhaka airport with National Martyrs’ Memorial in Savar via Abdullahpur, Ashulia, Dhaka EPZ and Chandra, with four intersections at Turag, Ashulia, Baipali and Chandra, said a report by Bangladesh University of Engineering and Technology (Buet), which was assigned by the Bridges Division for the project’s initial study.
However, according to the new plan, the expressway is now 22km and will connect Dhaka Airport with Baipali via Ashulia, with no intersections.
The construction work will begin next month, said Road Transport and Bridges Minister Obaidul Quader at a press briefing yesterday.
“We are backing away from the 42km plan because the road between Savar and Baipali is a four-lane road now, which was two-lane when we formulated the plan. There is also an immediate plan to upgrade it to a six-lane road in place. So the elevated expressway need not be 42km long,” Bridge Division Secretary Khandaker Anwarul Islam told the Dhaka Tribune.
Obaidul Quader said: “The elevated expressway will connect Baipali and Ashulia and the road between those two places cannot be upgraded to four-lane or six-lane road due to problems with land acquisition.”
The Dhaka-Ashulia Elevated Expressway is supposed to be an extension of the 26km Dhaka Elevated Expressway that will link the airport with Dhaka-Chittagong highway near Shanir Akhra to enable quick entry and exit of vehicles to and from Dhaka and facilitate transit trade with India, Nepal and Bhutan.
On January 22, the Bridges Division inked a memorandum of understanding (MoU) with China National Machinery IMP & EXP Corp (CMC) to construct the elevated expressway.
The project was approved in June 2011 at a meeting of the Cabinet Committee on Economic Affairs with an estimated cost of nearly $2 billion.
However, the CMC estimated almost double the original cost after completing their feasibility study in May, which the Bridges Division did not find acceptable.
“We have yet to cancel the MoU. The Economic Relations Division (ERD) has been given the charge of taking decisions regarding this project,” Anwarul Islam said.
The government had initially decided to implement the project under public-private partnership, and a notice was issued inviting tenders from investors by July 31, 2011, as per the directive of the cabinet committee.
But the tender invitation did not receive positive response and the government has not been able to find any investor to build the PPP project, which is why it decided to run the project under a government-to-government agreement, resulting in the MoU with the CMC.