Bangladesh Atomic Energy Regulatory Authority (Baera) will issue site licence to Rooppur Nuclear Power Plant project today to start proceedings of the main construction work.
The licence issuing ceremony, organised by the regulatory authority, will be held in a hotel in Dhaka, Professor Naiyyum Choudhury, chairman of Baera, told the Dhaka Tribune on Monday.
He said the licence will be given for a year – from July 2016 to July 2017. Under the licence, the project authority will conduct tests on soil stabilisation, meteorological study, safety and security.
If the work is not completed by August 2017, the project authority will not be given the construction licence to start the main construction work, the Baera chairman said.
The Rooppur project authority has already paid Tk3 crore to get the licence, he added.
Science and Technology Minister Yeafesh Osman, Prime Minister's Economic Affairs Adviser Mashiur Rahman, PMO Principal Secretary Md Abul Kalam Azad, Deputy Chairman of Rostechnadzor Alexey Ferapontov, Deputy Director General for International Relations of Rosatom Nikolai Spasskiy and Project Director of Rooppur Nuclear Power Plant Project Mohammad Shawkat Akbar will be present during the occasion.
State-owned Bangladesh Atomic Energy Commission, under the Science and Technology Ministry, will implement the Rooppur project.
On December 25 last year, Bangladesh and Russia signed a general contract for the construction and commissioning of the project in Pabna at a cost of $12.65 billion.
Bangladesh expects to add 2,400 MW of electricity to the national grid by 2023 from the nuclear plant at Rooppur with Russia’s support.