Dhaka airport Terminal-3 on runway for May takeoff  

  • PM reviews progress, pushes for May launch
  • Capacity to rise to 24m passengers annually
  • 37 aircraft parking bays, 177 check-in counters
  • 10 e-gates, 16 baggage belts installed
  • Around 6,000 staff needed for full operation
Update : 24 Feb 2026, 09:48 PM

After nearly eight years of delay, Hazrat Shahjalal International Airport’s much-discussed third terminal could finally become operational by May, following Prime Minister Tarique Rahman’s intervention at a high-level review meeting on Sunday.

The decision to accelerate preparations was taken at the meeting chaired by the prime minister, where officials were instructed to resolve pending operational and contractual issues without further delay.

Officials involved in the process said the terminal can be launched once an operator is formally appointed.

The Civil Aviation Authority of Bangladesh (CAAB) is expected to finalize the operation and maintenance agreement with a Japanese consortium within the next 10 to 15 days.

Civil Aviation Minister Afroza Khanam, however, refrained from announcing a definitive launch date.

“Further discussions and technical assessments are needed to expedite the process. Work is ongoing, but we cannot give a specific date at this moment,” she told reporters, adding that the prime minister has taken a proactive role in moving the project forward.

Capacity boost

Spread across 542,000 square metres, Terminal-3 is designed to significantly expand the airport’s capacity.

Passenger traffic at Hazrat Shahjalal International Airport continued to climb in 2025, with at least 12.72 million travelers passing through the country’s busiest gateway, according to airport sources.

The figure compares with 12.5 million passengers in 2024 and 11.7 million in 2023 -- an annual increase of about 223,000, or 1.8%.

Of the total passengers in 2025, around 10.31 million traveled on international routes, while 2.41 million flew domestically.

Designed to handle about 8 million passengers annually, Hazrat Shahjalal is now operating at nearly double its intended capacity.

Authorities expect relief once the new Terminal-3 becomes fully operational, enabling the airport to accommodate more than 20 million passengers a year.

Cargo capacity is projected to rise to 500,000 tons per year.

Operating the terminal will require around 6,000 personnel in four shifts, including nearly 4,000 security staff.

Eight years of delay

The third terminal project was approved in 2017 under the then Awami League government, with construction beginning on December 28, 2019.

The estimated cost stands at Tk21,398 crore. Of this, Tk5,000 crore was funded by the government, while the remainder came through a loan from the Japan International Cooperation Agency (JICA).

Although a soft inauguration was held on October 7, 2023, the terminal has yet to begin full operations.

CAAB officials attributed the delay to unresolved ground handling arrangements, technical glitches inside the terminal building, and disagreements over operational modalities with the Japanese consortium.

Sources said revenue-sharing terms proposed by the consortium were considered excessive, resulting in multiple inconclusive meetings last year.

Aviation analyst and former Biman board member Kazi Wahidul Alam said the prolonged delay has affected passengers and increased financial pressure.

“Eight years have passed since the project was taken up, yet it remains non-operational. Loan burdens have increased, and some equipment has already expired, which may require additional expenditure,” he told Dhaka Tribune.

He added that the uncertainty surrounding the launch timeline reflects administrative inefficiencies and called for a national-level expert committee to ensure swift operationalization.

Modern facilities awaiting activation

Terminal-3 includes a multi-storey car park with capacity for 1,044 vehicles and apron space for 37 aircraft.

The facility features 177 check-in counters, 64 departure and 64 arrival immigration desks, 16 baggage belts including four for oversized luggage, and automated e-gates for both departure and arrival passengers.

Import and export cargo terminals have also been incorporated into the new facility.

Under the proposed arrangement, Biman Bangladesh Airlines is expected to handle ground operations, while Japanese companies will manage commercial spaces, including retail outlets, lounges and restaurants.

With the prime minister now personally overseeing progress, officials say the coming weeks will be decisive in determining whether Bangladesh’s largest aviation infrastructure project can finally transition from inauguration to full-scale operation.