Bangladesh will pay Russia an additional $5 million for construction of the much-hyped Rooppur nuclear power plant as Moscow slashed its credit when signing the general contract in 2015.
Officials of Ministry of Science and Technology, with knowledge of the matter, said Russia reduced technical assistance of $5 million and this amount is going to be paid from government exchequer.
What prompted Russia's state-owned Rosatom to make the cut during the December 25, 2015 deal signing remains unclear.
The agreement stipulated that Bangladesh would have to pay $5 million or Tk40 crore.
The science and technology ministry's proposition to revise proposals of the general agreement is scheduled to be placed before the cabinet committee on public purchase this Wednesday.
According to the agreement, Russia is going to provide 90% of the funding – or $11.385 billion – as loan for constructing Rooppur plant.
The 2,400-megawatt plant will cost around $13.5 billion and Bangladesh will arrange the rest of the money.
According to Rosatom, the main construction work started in 2017 and the first unit is expected to go into production in 2022 and the second one a year later.
The first unit could be completed in 2024 and the second one in 2025.
Preparatory work to build the plant is underway under a $500-million technical assistance from Russia.
The interest rate will be maximum 4%, and the repayment period will be 28 years with a grace period of 10 years. The loan is neither concessional nor commercial.