The rail authorities also built the track using old slippers instead of new slippers, which may foil the main aim of the ‘Loop Line’.
Western Rail Division sources said the rail department had taken decision to build 500meters ‘Loop Line’ from Pakshi to Sirajganj Bazar railway station aiming to reduce shutting and coupling time, which was secluded to inaugurate finally on December 11, this year.
Maxwell Compant Limited, a Dhaka-based constructor company got the work tender, started to work in this year and completed the works within December 1, which was secluded as inaugurate day first.
Later, to inspect the track rail authorities run a trail train On November 23. During the trail run, railway engineers found that workers could not couple the engine as the line is not strait as needed. Engineers found that it was caused due to design fault.
After this incident, authorities deferred the inauguration date and fixed December 11 as new inauguration date.
When conatced, Ashraf Uddin, senior deputy assistant engineer (PW-I) of Sirajganj Western Rail Division, confessed to the Dhaka Tribune that they built the ‘Loop Line’ without any design.
He said: “We just followed the orders from higher officials, we do not know anything about design.”
Wishing anonymity several officials of Sirajganj Western Rail Division said all efforts to reduce the journey time of train are going in vein as Sirajganj Western Rail Division authorities built the ‘Loop Line’ as their methods without any design.
They also alleged that the ‘Loop Line’ may have become a burden for Sirajganj Western Rail Division.
On the other hand, locals alleged that the railway authorities also used old slippers in the line instead of new slippers.
When contacted, officials of Sirajganj Western Rail Division said that due to lack new slippers they have bound to supply old slippers.